A technology of full-section grouting and coal mine roadway, which is applied in tunnels, tunnel linings, mining equipment, etc., can solve the problems of frequent equipment handling, unreasonable procedures, and high labor intensity, so as to improve the efficiency of grouting construction and reduce auxiliary projects The effect of reducing labor intensity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0014] The present invention will be further described in conjunction with the accompanying drawings.
[0015] A full-section grouting construction method for a coal mine roadway, comprising the following steps:
[0016] In the first step, according to the layout parameters of the grouting reinforcement drilling in the surrounding rock of the coal mine roadway, when the roadway side and the roadway roof are arranged with grouting reinforcement drilling holes in a section, the drilling construction of the roadway side grouting drilling is carried out first , and then carry out the drilling construction of the grouting drilling on the roof of the roadway. After completing the construction and grouting of all the grouting drilling in the same section, move the drilling rig to construct the drilling of the next section;
[0017] In the second step, after the construction of the roadway side and the roadway roof grouting reinforcement of the same section is completed, the boreholes...