Unlock instant, AI-driven research and patent intelligence for your innovation.

Deep-water shallow-covering-layer full-rock-socketed bridge foundation construction method

A technology of bridge foundation and construction method, applied in basic structure engineering, bridge, bridge construction and other directions, can solve the problems of poor material turnover, difficult underwater blasting construction, large amount of back cover concrete, etc., and is conducive to navigation safety. and flood control requirements, reducing the amount of over-excavation and backfilling works, and reducing the effect of clearing ship machinery equipment

Inactive Publication Date: 2021-04-06
CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP 1ST ENG
View PDF23 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, underwater blasting construction is difficult, with high safety risks and high costs. The progress of cleaning the foundation pit is uncontrollable due to the influence of silting. At the same time, the amount of steel used in the steel cofferdam is large, and the turnover of materials is not strong. It requires an assembly site and a large amount of concrete for the bottom cover , the overall cost is high, and the overall floating and lowering of the steel cofferdam has high requirements on ship machinery equipment and navigation conditions, while the bulk steel cofferdam not only uses a large amount of materials, but also has a slow construction progress

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Deep-water shallow-covering-layer full-rock-socketed bridge foundation construction method
  • Deep-water shallow-covering-layer full-rock-socketed bridge foundation construction method
  • Deep-water shallow-covering-layer full-rock-socketed bridge foundation construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0033] The specific implementation manner of the present invention will be described below with reference to the accompanying drawings. Such as Figure 1 to Figure 10 Shown: A construction method for a deep-water shallow overburden fully rock-socketed bridge foundation, which is carried out in the following order:

[0034] a. If figure 1 As shown, first build a steel trestle 1 and a steel platform 2 on the water as temporary facilities for bridge foundation construction on the water,

[0035] b. If figure 2 As shown, the steel casing 19 for pile foundation construction above the water is installed on the steel platform 2, and the steel trestle 1 is used to construct the locking steel pipe pile cofferdam 3 along the sideline of the designed cap 18 at the same time. In order to ensure accurate construction, the construction During the process, the guide frame 4 is used as a construction aid,

[0036] c. If image 3 As shown, the pile foundation equipment 5 is installed on ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a deep-water shallow covering layer full-rock-socketed bridge foundation construction method which is sequentially carried out according to the following steps that firstly, a steel trestle and a steel platform are built on water, and then a lock catch steel pipe pile cofferdam is constructed outside the side boundary of a designed bearing platform; pile foundation equipment and constructing pile foundations are installed on a steel platform, hole guiding and re-vibration are synchronously conducted on the lock catch steel pipe pile cofferdam, and a pipe and a hole are filled with fillers at a certain height to solidify the bottom of the cofferdam; a temporary platform is erected through a gap between the steel trestle and the steel platform, grouting equipment is installed, and curtain grouting and water stopping are conducted on shallow coverage; the steel platform in the steel cofferdam is removed, water is pumped, and purlin supports are installed step by step until a water-free operation environment is formed in the cofferdam; a steel casing for pile foundation construction is cut off, excavation equipment is lowered, and a shallow covering layer and soft stone are cleaned; and a construction intercepting ditch is used for intercepting water, if water leaks in the cofferdam, plugging is conducted in time, and curtain grouting water stopping and the like are conducted in the cofferdam.

Description

technical field [0001] The invention relates to the technical field of bridge foundation construction, in particular to a construction method for a deep-water shallow overburden fully rock-socketed bridge foundation. Background technique [0002] my country's bridge engineering construction level has been among the top in the world, and it can cross various complex obstacles such as valleys, rivers, lakes and seas, and has achieved brilliant achievements. When some bridges cannot cross the river due to structural limitations, it is necessary to set up pier foundations in the water to meet the span requirements. When setting up pier foundations in water, it is necessary to meet the flood control assessment requirements such as water blocking, backwater, and scour, and if it crosses a channel, it must also meet the navigation guarantee requirements. There is an existing bridge foundation. In order to meet the requirements of flood control and navigation, the bridge foundation...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00E02D27/12E02D27/52E02D19/04E02D19/18E02D5/38
CPCE01D21/00E02D27/12E02D27/52E02D19/04E02D19/18E02D5/38
Inventor 彭志川孙长志张广涛林凤国姜相松王正陶中原王伟孙成利张壮壮赵艳龙刘延斌
Owner CHINA RAILWAY CONSTR BRIDGE ENG BUREAU GRP 1ST ENG