Intelligent construction method and system for near subway building
A construction method, technology close to the subway, applied in special data processing applications, instruments, data processing applications, etc., can solve problems such as poor deformation control effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment approach
[0037] As a preferred embodiment of the present invention, it also includes:
[0038] Set the threshold of deformation change. After the deformation trend of the area is obtained, compare the deformation trend with the threshold. If the deformation trend will exceed the threshold, an alarm will be issued.
[0039] Further, it also includes:
[0040] Track the construction materials and personnel to obtain the logistics information of construction materials and personnel, and predict the arrival time of construction materials and personnel according to the logistics information, so as to adjust the construction plan, and then deploy personnel and materials according to the logistics information, To improve construction efficiency.
[0041] Preferably, the logistics information of the material can be uploaded by scanning the two-dimensional code on the material, and the logistics information of the personnel can be obtained by sharing the location information of the constructio...
specific Embodiment approach
[0043] Before construction, use BIM technology and finite element analysis technology to establish a model of the building to be constructed and conduct simulation deduction, that is, conduct construction simulation, determine the point with the largest deformation and the deformation trend of the point, and formulate a corresponding disposal plan to control the settlement at that point;
[0044] Carry out construction according to the simulated working conditions and disposal plan, and monitor the construction site to obtain the deformation data of the surrounding subway, the deformation data of the excavated foundation pit, and the groundwater level change data to obtain the construction site corresponding to the point. The amount of deformation in the area and the deformation trend of the area. According to the deformation trend, the construction conditions of the model are corrected, and the simulation deduction is performed again. The actual deformation data can be obtaine...