The present application relates to the field of building decoration waterproof construction technology, and discloses a bathroom waterproof construction, closed water
verification and finished product protection
closed loop control method, comprising the following specific steps: cleaning, leveling and
drying treatment of the bathroom base layer to form a base layer surface suitable for waterproof
coating adhesion; additional reinforcement is made on high-risk nodes such as doorways, inside and outside corners,
pipe roots, floor drains and
water supply points, and an extended waterproof area and an end visual
humidity detection point are formed outside the doorway. Then, waterproof
coating is applied in multiple passes, and at least
one pass is identified for surface defects and repaired for re-inspection. After film formation, the first finished product protection state is switched and the first closed water test is performed, and the
water level is observed or blocked for detection outside the doorway simultaneously; if qualified and no
water leakage occurs, controlled construction of the
protection layer is allowed, otherwise, the position is repaired and re-inspected. The second finished product protection state is switched during and after the construction of the
protection layer, and the second closed water test is performed; after passing, the tiling or decoration process is handed over, and if unqualified, the
protection layer is repaired and re-inspected. The present application solves the problems of bathroom waterproof node leakage, closed water and finished product protection disconnection, and subsequent construction damage to the waterproof layer.