Heavy haul railway tunnel group ballastless track and construction method thereof
A ballastless track and tunnel group technology, applied in the direction of track, movable track, laying track, etc., can solve the problem that the accurate detection and maintenance of loose fasteners cannot be realized, and achieve the effect of convenient maintenance process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0046] Embodiment 1: The embodiment of this application discloses a ballastless track of a group of heavy-duty railway tunnels.
[0047] refer to figure 1, the ballastless track of the heavy-duty railway tunnel group includes a concrete base 1 , a plurality of track slabs 2 and two rows of linear rails 3 . Several track slabs 2 are divided into two rows, and are equidistant side by side and arranged transversely on the concrete base 1, so as to realize the support of the steel rail 3.
[0048] refer to figure 1 , figure 2 A pair of shoulders 21 are provided on both ends of the track slab 2, and the rail 3 is laid on the track slab 2, and is located between each pair of shoulders 21, so as to limit the position of the rail 3. A pair of fasteners 22 are arranged between each pair of retaining shoulders 21 , and the pair of fasteners 22 are distributed on both sides of the rail 3 and press against the sidewalls of the lower ends of the rail 3 .
[0049] refer to figure 1 , ...
Embodiment 2
[0074] Embodiment 2: The embodiment of this application discloses a construction method for ballastless track of heavy-duty railway tunnel group.
[0075] The construction method of the ballastless track of the heavy-duty railway tunnel group comprises the following steps:
[0076] S1, install the steel bars of the bottom plate of the ballast bed, and pour the concrete at the bottom;
[0077] S2, install the base reinforcement, the concrete base 1, and maintain the concrete base 1;
[0078] S3, laying the prefabricated track slabs 2 equidistantly on the concrete base 1, and pouring concrete to fix the track slabs 2;
[0079] S4, laying the rail 3, and calibrating the rail 3;
[0080] S5, install the fastener 22, and tighten the bolt 23 into the embedded pipe 24 on the track plate 2, so as to realize the fixing of the fastener 22 and the rail 3;
[0081] S6, installing the airbags 5, and filling the colored detection liquid into each airbag 5;
[0082] S7, install the feedb...