Steel truss bridge deck slab hoisting construction method under limited clearance condition
A technology of steel truss bridges and construction methods, applied in the direction of erecting/assembling bridges, bridges, bridge parts, etc., can solve problems such as difficult hoisting and insufficient clearance, and achieve the purpose of solving insufficient clearance, optimizing the structure of bridge erecting machines, and good reference significance Effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0024] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0025] A construction method for steel truss bridge deck hoisting under the condition of limited clearance, the main construction sequence is as follows, the hoisting process of the whole construction process is as follows: Figure 2 to Figure 9 Shown:
[0026] Step 1: Construction preparation, this step mainly includes the following construction contents:
[0027] (1) Carry out a comprehensive analysis based on the hoisting conditions of the full bridge box girder and bridge deck, and determine that the hoisting equipment adopts the bridge erecting machine;
[0028] (2) Calculation and analysis of net height of steel truss and height of bridge erecting machine, such as figure 1 Shown is the elevation of the steel truss bridge portal;
[0029] (3) Organize the bridge erecting machine to enter the site for assembly according to the ...