Construction method for underneath passing of existing railway through three-hole highway tunnel
A construction method and existing railway technology, applied in tunnels, tunnel linings, underground chambers, etc., can solve problems such as road and railway tunnel construction, improve travel efficiency and reduce traffic accidents
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0029] Embodiment 1: A construction method for passing through an existing railway under a three-hole highway tunnel, comprising the following steps:
[0030] S1. The construction adopts the drilling and blasting method to blast the two main holes and the intermediate pilot hole. In step S1, the drilling and blasting method is a construction method that uses explosive blasting to break the rock mass and open the cavern. S1 The main hole is treated and reinforced The distance between the working face and the unfavorable geological zone shall not be less than 10m;
[0031] S2. After the assembly and commissioning of the open tunnel boring machine is completed, the drilling and blasting construction of the intermediate pilot tunnel is stopped, and the open tunnel boring machine advances to the working face of the intermediate pilot tunnel, so that the open tunnel boring machine can excavate and produce, and the two main tunnels continue Drill and blast construction;
[0032] S3....
Embodiment 2
[0041] Embodiment 2: A construction method for passing through an existing railway under a three-hole highway tunnel, comprising the following steps:
[0042] The construction method for passing through the existing railway under the three-hole highway tunnel is characterized in that it comprises the following steps:
[0043] S1. The construction adopts the drilling and blasting method to blast the two main holes and the intermediate pilot hole. In step S1, the drilling and blasting method is a construction method that uses explosive blasting to break the rock mass and open the cavern. S1 The main hole is treated and reinforced The distance between the working face and the unfavorable geological zone shall not be less than 10m;
[0044] S2. After the assembly and commissioning of the open tunnel boring machine is completed, the drilling and blasting construction of the intermediate pilot tunnel is stopped, and the open tunnel boring machine advances to the working face of the ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com