Rapid replacement method for fixed section flue of large converter
A replacement method and technology for large-scale converters, which are applied in the directions of manufacturing converters, improving process efficiency, and improving energy efficiency, can solve the problems of reduced construction efficiency, low construction efficiency, inconvenient installation and operation, etc., so as to reduce potential safety hazards and shorten construction. time, the effect of reducing the demolition process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0044] A method for quickly replacing the flue in a fixed section of a large-scale converter, which specifically includes the following steps:
[0045] Step 1: Preparations
[0046] 1.1 Before the converter is shut down, make a temporary construction platform (such as figure 1 and 2 As shown), the temporary construction platform 9 is a regular octagon, including platform panel 1 (with pattern on the top) and platform outrigger 2 (made of I-beam, whose length is confirmed according to the size of the converter support ring to the furnace mouth), the platform panel A plurality of platform outriggers 2 perpendicular to the platform panel 1 are welded below the platform panel 1, channel steel clad beams are provided on the outer edge of the platform panel 1, and a fence 3 is also provided on the outer edge of the upper side of the platform panel 1 to ensure construction safety;
[0047] 1.2 Before the converter is shut down, according to the size of the flue in the fixed section...
PUM