Construction method of system-level power failure maintenance plan standard construction period calculation system

A technology of standard construction period and maintenance plan, applied in computing, data processing applications, instruments, etc., can solve the problems of reducing maintenance work efficiency, insufficient construction period, waste of resources, etc., to improve scientificity, avoid waste of resources, and improve maintenance efficiency. Effect

Pending Publication Date: 2022-04-29
NARI NANJING CONTROL SYST +1
View PDF0 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

In order to avoid insufficient construction period of the maintenance plan, the construction period declared based on experience is often much longer than the actual required construction period, resulting in a waste of resources and reducing the work efficiency of the maintenance business

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of system-level power failure maintenance plan standard construction period calculation system
  • Construction method of system-level power failure maintenance plan standard construction period calculation system
  • Construction method of system-level power failure maintenance plan standard construction period calculation system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0020] The present invention will be further described below in conjunction with the accompanying drawings. The following examples are only used to illustrate the technical solution of the present invention more clearly, but not to limit the protection scope of the present invention.

[0021] A method for constructing a system-level power outage maintenance plan standard construction period calculation system, including: according to the four dimensions of area, equipment type, voltage level, and equipment capacity, define the construction period reference value of each type of equipment in the system layer by layer, and construct a system-level power outage maintenance plan standard The first five-layer structure of the construction period calculation system; based on the first five-layer structure, the maintenance type layer is generated according to the maintenance type as the sixth layer structure, and the initial benchmark value of each unit set is generated by using the h...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a system-level power failure maintenance plan standard construction period calculation system in the technical field of electric power maintenance. The construction method comprises the following steps: constructing first five layers of structures of the system-level power failure maintenance plan standard construction period calculation system according to areas, equipment types, voltage classes and equipment capacities; determining a sixth-layer structure according to the maintenance type, generating an initial reference value of each unit set by using historical maintenance period information, generating a standard construction period calculation formula of different maintenance types in each unit set based on the construction period reference value, and performing correction; and by taking the minimum sum of the sum of the historical maintenance period of each device in the unit set and the absolute value of the calculated difference value of each standard construction period as an optimization target, simulating a standard construction period calculation formula of a maintenance type without historical maintenance period information in the unit set, and completing the construction of a seventh layer. According to the method, the standard construction period under related equipment maintenance types without historical data support can be obtained, resource waste caused by unreasonable construction period setting is avoided, and the maintenance efficiency is improved.

Description

technical field [0001] The invention belongs to the technical field of electric power maintenance, and in particular relates to a method for constructing a system-level power outage maintenance plan standard construction period calculation system. Background technique [0002] The maintenance period is an important index to evaluate the workload of the maintenance plan. When applying for a power outage maintenance plan, the power company needs to fill in the start time, end time and maintenance period of the maintenance plan. The maintenance period is directly related to the length of the maintenance plan execution period (the end time minus the start time). In many areas, the maintenance plan is directly The length of the execution period shall be declared and reviewed as the maintenance period. [0003] When the power company declares and reviews the maintenance plan, it can often make scientific arrangements for when the power outage maintenance plan will start to be imp...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/06G06Q10/00G06Q50/06
CPCG06Q10/063118G06Q10/20G06Q50/06
Inventor 赵浚婧昌力彭虎张彦涛吴炳祥杨鹏程杨洋徐昊
Owner NARI NANJING CONTROL SYST