Apron board machining device for concrete pipe pile and using method of apron board machining device
A technology for concrete pipe piles and processing devices, which is applied to sawing machine devices, metal processing, positioning devices, etc., can solve the problem of poor combination performance of the rib-pressing device and the rounding device, unfavorable positioning and processing of the rib-pressing device, and the fit performance of the discharging device. Variation and other problems, to achieve the effect of solving poor bonding performance, achieving precise docking, and improving stability
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0054] refer to Figure 1-10 , a skirt plate processing device for concrete pipe piles, comprising:
[0055] Intermittent conveying mechanism 10, used for intermittent conveying of apron blank;
[0056] Auxiliary positioning mechanism 20, installed on the intermittent conveying mechanism 10, is used for positioning during the conveying process of skirt blank;
[0057] The discharge guide mechanism 30 is arranged at the front end of the intermittent conveying mechanism 10, and is used for coil feeding of the skirt blank;
[0058] The smoothing mechanism 40 is installed on the intermittent conveying mechanism 10, and is positioned at the rear of the discharge guide mechanism 30, and is used to level the apron blank delivered to the smoothing mechanism 40;
[0059] The cutting mechanism 50 is installed above the intermittent conveying mechanism 10, and is used to cut the apron blank delivered to the cutting mechanism 50;
[0060] The positioning support circle welding mechanis...
Embodiment 2
[0074] refer to figure 1 and Figure 4 , a skirt plate processing device for concrete pipe piles, which is basically the same as that of Embodiment 1. Further, the material return assembly 70 includes a T-shaped frame 710 installed on the outer wall of the installation rod 610 near the top, symmetrically installed on the T-shaped frame The fourth electric telescopic rod 720 of the 710 horizontal section and the pusher plate 730 installed on the telescopic end of the fourth electric telescopic rod 720, after the welding is completed, open the fourth electric telescopic rod 720 on the material return assembly 70, and drive the pusher plate 730 to The steel coil is pushed away by the positioning roller 620 to realize the function of blanking.
PUM