A technology of permeable concrete and preparation process, which is applied to cohesive pavement, roads, side ditches/curbs and other directions paved on site, which can solve the burden of flood control and drainage in urban and rural residential areas, affect the environment and social development, and drainage efficiency Low-level problems, to achieve the effect of increasing overall stability, increasing strength, and promoting drainage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] The present embodiment also provides a process for preparing a water-permeable concrete structure, comprising the following steps:
[0031] Step 1: After the two drainage grooves 8 are placed stably, the soil is laid on the periphery of the drainage grooves 8 to form a soil layer 1, and four slopes inclined 5° toward the drainage grooves 8 are arranged on the top of the soil layer 1 and then compacted;
[0032] Step 2: Lay anti-seepage geotextile 2 on top of soil layer 1;
[0033] Step 3: Lay the gravel layer 3 on the slope between the soil layer 1 and the drainage channel 8 and level it so that the soil layer 1 and the gravel layer 3 and the top of the drainage channel 8 are all at the same level;
[0034] Step 4: After the permeable plate 6 is covered on the top of the drainage groove 8, and the two ends are supported on the soil layer 1, after continuing to spread the gravel layer 3, a 500kg small road roller is used for vibration compaction;
[0035] Step 5: 1000 p...
Embodiment 2
[0038] The present embodiment also provides a process for preparing a water-permeable concrete structure, comprising the following steps:
[0039] Step 1: After the two drainage grooves 8 are placed stably, the soil is laid on the periphery of the drainage grooves 8 to form a soil layer 1, and four slopes inclined 5° toward the drainage grooves 8 are arranged on the top of the soil layer 1 and then compacted;
[0040] Step 2: Lay anti-seepage geotextile 2 on top of soil layer 1;
[0041] Step 3: Lay the gravel layer 3 on the slope between the soil layer 1 and the drainage channel 8 and level it so that the soil layer 1 and the gravel layer 3 and the top of the drainage channel 8 are all at the same level;
[0042] Step 4: After the permeable plate 6 is covered on the top of the drainage groove 8, and the two ends are supported on the soil layer 1, after continuing to spread the gravel layer 3, a 500kg small road roller is used for vibration compaction;
[0043] Step 5: 1250 p...
Embodiment 3
[0046] The present embodiment also provides a process for preparing a water-permeable concrete structure, comprising the following steps:
[0047] Step 1: After the two drainage grooves 8 are placed stably, the soil is laid on the periphery of the drainage grooves 8 to form a soil layer 1, and four slopes inclined 5° toward the drainage grooves 8 are arranged on the top of the soil layer 1 and then compacted;
[0048] Step 2: Lay anti-seepage geotextile 2 on top of soil layer 1;
[0049]Step 3: Lay the gravel layer 3 on the slope between the soil layer 1 and the drainage channel 8 and level it so that the soil layer 1 and the gravel layer 3 and the top of the drainage channel 8 are all at the same level;
[0050] Step 4: After the permeable plate 6 is covered on the top of the drainage groove 8, and the two ends are supported on the soil layer 1, after continuing to spread the gravel layer 3, a 500kg small road roller is used for vibration compaction;
[0051] Step 5: 1500 pa...