Railway large-bore tunnel overhead contact built-in sliding chute construction method
A tunnel contact and construction method technology, applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve the problems of slow installation progress, low safety and durability, and uneven appearance, and achieve simple reinforcement, improved work efficiency, and smooth appearance Effect
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Publication Date
- 2008-05-21
Smart Images
Figure 1
Abstract
Description
technical field
[0001] The invention relates to the technical field of railway tunnel construction, in particular to a construction method for a catenary pre-embedded chute in a large-section railway tunnel. Background technique
[0002] It is well known that the pre-embedding process of the catenary of large-section railway tunnels plays a very important role in the entire construction process. Now the most commonly used embedded part is the slideway groove, which can withstand a tensile force of 22KN, which can fully meet the requirements of the catenary. For the load inherited by the suspension column, the pre-embedded foundation of the catenary suspension column adopts two channels welded together in parallel through flat steel, and the method usually used for the embedded slideway groove is the chemical anchoring method. In actual use, it needs to be erected and installed The process of rigging, sending additional personnel to dig grooves, installing embedded parts, and...
Examples
Embodiment Construction
[0011] A method for constructing pre-embedded chutes in railway large-section tunnel catenary, comprising the following steps: (1) Opening holes in the formwork of the lining trolley: according to the embedding position, quantity, length and spacing of the chutes in the lining, determine the position on the formwork of the lining trolley. The opening position of the positioning hole, the positioning hole is a rectangular hole, and the size is length × width = 4 × 2cm; (2) The positioning of the lining trolley: it is determined according to the distance between the catenary suspension columns, the processing length of the lining trolley and the actual construction length of the lining concrete The overlapping length of the lining trolley and the poured lining is generally 8-10cm. When measuring and setting out, the mileage control point is accurately determined on the inverted arch filling surface according to the actual construction length of the lining concrete and the total le...