Method for rolling seamless steel pipe from die-casting hollow steel ingot
A seamless steel pipe and hollow steel technology, applied in the field of metallurgy, can solve the problems of seamless steel pipes without die-casting hollow steel ingots, and achieve the effects of large-scale production, expansion of production varieties, and easy heating
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Examples
Embodiment 1
[0026] Example 1 P22 steel grade die-casting hollow steel ingot adopts the method of the present invention to roll seamless steel pipe
[0027] Rolling specifications: φ480×22.5, φ457.2×33
[0028] Production process flow: die-casting hollow steel ingots → ring furnace heating → piercing machine extension → periodic tube rolling → steel tube finishing → packaging and storage.
[0029] Process parameters of each process: ring furnace heating temperature control: ring furnace cycle production, first use the residual heat in the furnace to gradually raise the temperature of the ingot (time is 1.5 hours), the temperature settings of the 6-stage heating treatment are: preheating stage 1, 1080 ℃ ~1150℃(heating time 1.5 hours), preheating stage II 1180℃~1240℃(heating time 2.0 hours), heating stage I 1240℃~1260℃(heating time 1.5 hours), heating stage II 1250℃~1280℃( Heating time 2.0 hours), soaking stage I 1270°C~1280°C (heating time 1.5 hours), soaking stage II 1270°C~1280°C (heating time ...
Embodiment 2
[0031] Example 2 The 27SiMn steel grade die-casting hollow steel ingot was used to roll seamless steel pipes using the method of the present invention
[0032] Rolling specifications: φ396×60, φ457×45
[0033] Production process flow: die-casting hollow steel ingots → ring furnace heating → piercing machine extension → periodic tube rolling → steel tube finishing → packaging and storage.
[0034] Process parameters of each process: ring furnace heating temperature control: ring furnace cycle production, first use the residual heat in the furnace to gradually raise the temperature of the ingot (time is 2.0 hours), the temperature settings of the 6-stage heating treatment are: preheating section 1, 1080 ℃ ~1140℃(heating time 2.0 hours), preheating stage II 1180℃~1230℃(heating time 2.0 hours), heating stage I 1240℃~1250℃(heating time 1.5 hours), heating stage II 1250℃~1270℃( Heating time 1.0 hour), soaking stage I 1260°C~1270°C (heating time 1.5 hours), soaking stage II 1260°C~1270°C (...
PUM