High-speed thermal circulation air curtain construction method for tunnel portal
A construction method and thermal cycle technology, applied in the ventilation, heating, space heating and ventilation directions of mines/tunnels, which can solve the problems of freezing tunnel mouths and affecting traffic safety, reduce heat demand and stabilize station temperature. , the effect of driving safety
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0016] Embodiment one: if figure 1 As shown, the present embodiment installs a group of air handling units 2 on one side of the tunnel entrance 1, and the air heated and pressurized by the air handling units 2 sprays the hot air curtain at a high speed through the air outlet 3 and the high-speed nozzle 4 connected to the air outlet. A circulating air duct 6 is set at the position where the hot air curtain flows on the other side of the tunnel, and the hot air curtain flows back through the circulating air duct 6 and the cross-track air duct 7 to the circulation chamber 8 connected to the air inlet 9 of the air handling unit, and then enters the air handling unit 2. Complete the circulation of the hot air curtain.
[0017] Among them, the wind speed of the hot air curtain ejected from the high-speed nozzle 1 must not be less than 20 m / s, so as to eject a high-speed airflow with a certain thickness and form a thick hot air curtain at the cave entrance to block the invasion of ex...
Embodiment 2
[0019] Embodiment two: if figure 2 As shown, in this embodiment, a group of air handling units 2, high-speed nozzles 4 and circulation chamber 8 are respectively installed on both sides of the tunnel, and two hot air curtains are generated at the entrance of the tunnel, and the hot air curtains generated on one side are blown to the other side The circulation chamber 8 forms a circulating hot air curtain. The wind speed of the hot air curtain ejected by the high-speed nozzle 4 must be no less than 20 m / s, and the installation angle of the high-speed nozzle 4 must ensure that the hot air curtain flows to the circulation chamber 8 on the other side.
[0020] When it is a parallel double-hole tunnel running on two lines, a channel 10 is set on the tunnel partition wall 12 that the hot air curtain flows through, and a fireproof roller shutter can be installed on the channel 10 . A detour air duct 11 is arranged on the partition wall 12 of the parallel double tunnel tunnel.
[0...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com