It is a technology for strengthening existing buildings and foundations, which is applied in the fields of architecture, infrastructure engineering, and soil protection. It can solve the problems that the upper structure cannot be provided, the design theory does not conform to the design theory, and the reinforcement is not easy. It achieves low hydration temperature rise, Effect of reducing dust pollution and reducing usage
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
example 1
[0031] The existing building to be reinforced in this embodiment is a one-story building with a large space at the bottom, with an independent foundation under the column, and the foundation is buried at a depth of 1.80m. Due to the subsidence of the foundation, the entire building will sink.
[0032] Step 1. After field investigation, identification and analysis, the construction parameters are determined as follows: 24 piles are used, 2 piles under each foundation, the distance between the 2 piles under each foundation is 1400mm, and the pile hole is d=600mm , the pile length is 11m;
[0033] Step 2. According to the construction parameters determined in Step 1, excavate a 1-2m wide construction trench at the foundation of the existing building, and manually dig holes to form pile holes, inspect the soil quality, and clean the debris at the bottom of the hole;
[0034] Step 3: The stones used for the pile body are 2-20 cm block stones, the concrete strength is C20, and the b...
example 2
[0038] In this embodiment, the required reinforced building is a single-story bent frame structure with an independent foundation under the column, and the foundation burial depth is 2.10 m. After the building was used, it was found that there were cracks in the wall and the ground, and there was a tendency to expand. In order to prevent the cracks in the ground and walls of the plant from continuing to develop and cause damage to the structure, effective reinforcement measures should be taken.
[0039] Step 1. After field investigation, identification and analysis, the construction parameters are determined as follows: 50 piles are used, 2 piles under each foundation, the distance between 2 piles under each foundation is 1000mm, and the pile hole is d=800mm , The pile length is 13m.
[0040] Step 2, excavating construction grooves and manually digging holes to form pile holes;
[0041] Step 3: Use pebbles with a particle size of 2-20 cm for the pile body, the concrete streng...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com