Waste gas dust removal system for calcium carbide furnace
A technology of dust removal system and calcium carbide furnace, which is applied in the separation of dispersed particles, chemical instruments and methods, and the use of liquid separation agents, etc., can solve the problems of polluting the environment, generating a large amount of smoke, and poor dust removal effect.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0017] As shown in Figure 1, a calcium carbide furnace waste gas dust removal system, the top outlet of the waste gas chimney 1 of the calcium carbide furnace is connected to the waste gas venting pipe 2 obliquely downward, and one end of the recovery main pipe 3 of the calcium carbide furnace is connected to the waste gas obliquely upward The vent pipe 2 and the scrubber 4, the other end of the recovery main pipe 3 extends into the pool 6, and three first nozzles 5 are arranged in the waste gas vent pipe 2, and the water volume of each first nozzle 5 is 50m 3 / h, six second nozzles 6 are set in the scrubber 4, respectively located at different heights, and the water volume of each second nozzle 6 is 20m 3 / h, the first nozzle 5 is provided with a cut-off valve, and is interlocked with the waste gas valve of the waste gas chimney 1 .
[0018] For the convenience of maintenance, a pair of flanges with 8-shaped blind plates are arranged on the top of the waste gas chimney 1, and...
Embodiment 2
[0022] A calcium carbide furnace waste gas dust removal system. There are eight calcium carbide furnaces in the same row, which are the first to eighth calcium carbide furnaces in sequence. The top outlet of the waste gas chimney 1 of each calcium carbide furnace is connected to the obliquely downward waste gas. The venting pipe 2 and the scrubber 4 are arranged between the fourth and fifth calcium carbide furnaces, and the waste gas venting pipes 2 on the first, second, third and fourth calcium carbide furnaces are sequentially connected with the one on the slant upward. The recovery main pipe is connected, and the waste gas venting pipe 2 on the eighth, seventh, sixth and fifth calcium carbide furnaces is connected with another recovery main pipe on the slant in turn. Pools 6 are arranged symmetrically at the positions respectively, and the pools 6 communicate with the corresponding recovery main pipes, and communicate with the corresponding first nozzle 5 and the second nozz...