Electric mold lifting construction method of chimney
A construction method and chimney technology, applied in the direction of formwork/formwork/work frame, building type, preparation of building components on site, etc., can solve the problems of labor cost, a large amount of racking materials, and the inability to install climbing boots, etc., and achieve saving The effect of manpower, reduction of construction period and construction cost, reduction of operational risk and construction difficulty
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0021] A kind of chimney electric formwork lifting construction method of the present invention, comprises the following steps: A, according to conventional formwork turning construction technology, carry out construction to chimney tube wall 1 below 6 meters and reserve the wall-through screw hole that climbing boot is installed At the same time, according to the load of the electric mold lifting device, the position and size of the chimney opening, multiple rows of horizontal pre-insertion rods 2 and vertical pre-insertion rods 3 are pre-inserted on the two side walls 12 and the bottom wall 13 of the chimney opening 11 respectively ( Such as Figure 4 , Figure 5 As shown, it is the case of pre-inserting two rows of horizontal pre-insertion rods 2 and vertical pre-insertion rods 3 respectively on the two side walls 12 and bottom wall 13 of the chimney opening 11); B, corresponding to the chimney wall 1 on the ground Position assembly electric mold lifting device 8; C, betwe...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 