Monitoring method for rapid load reduction of power plant set
A technology of load reduction and generator set, applied in the field of measurement, can solve problems such as long recovery time
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0040] The present invention will be further described below using the embodiments shown in the accompanying drawings.
[0041] refer to figure 1 , taking a certain 300MW unit as an example, a monitoring device for rapid load reduction of a power plant unit of the present invention, including the electrical connection between the DCS of the generator unit and the USB interface of the monitoring computer; Electrically connected, the temperature measuring resistor is electrically connected to the data collector, the pressure transmitter and differential pressure transmitter electrically connected to the generator set are electrically connected to the piezoresistor, the piezoresistor is electrically connected to the data collector, and the data collector is electrically connected to the electric Connect the thermocouple installed on the steam drum of the boiler to the temperature measuring resistor, the temperature measuring resistor to the data collector, and the data collector...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 