A self-floating, manpower technology, applied in underwater structures, infrastructure engineering, artificial islands, etc., can solve the problems of high construction cost, large amount of engineering, inability to achieve rapid construction of elevated structures, etc., and achieve the effect of light structure
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0024] The use of elevated structure equipment usually includes the following steps:
[0025] ① Elevated structure equipment is transported by ship to the sea area near the area to be erected;
[0026] ② Utilize the lifting equipment of the transport ship or through the relevant auxiliary sliding mechanism to implement flooding of the elevated structure equipment, the pile legs (4) and the auxiliary structure of the elevated structure and the auxiliary erection tools can be tied to the upper airtight box (1) of the elevated structure, The buoyancy of the box can ensure that the elevated structure equipment floats on the water surface;
[0027] ③Use small boats or manpower to haul the upper airtight box (1) (together with the pile legs (4), auxiliary structures and erection aids tied to it) to the erection zone;
[0028] ④ Install or connect the pile leg (4) and the foundation plate (7);
[0029] ⑤ Put down the pile legs (4) to make the base plate (7) contact with the bottom ...