A construction method and technology for entering and exiting holes, which are applied in earth-moving drilling, mining equipment, tunnels, etc., can solve problems such as high construction risks, and achieve the effects of ensuring the safety of entering and exiting holes, saving construction time, and reducing project costs.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0012] In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
[0013] A construction method for shield tunnel entry and exit, comprising the following steps:
[0014] (1) After the main structure of the shield well is completed, the underground diaphragm wall is used as the enclosure structure, and glass fiber bars are used to replace the steel bars of the ground connection wall at the portal where the shield machine passes through the groove wall of the ground connection wall;
[0015] (2) Build a reinforced concrete box in front of the portal and backfill it with soil to seal it. When the shield tunnel starts, the backfill soil seals the shield machine in th...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com