Construction method for reinforcing broken geology around pile
A technology of crushing geology and construction method, applied in soil protection, infrastructure engineering, construction, etc., can solve the problem of pile foundation hole forming process that cannot be guided and so on
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0025] A construction method for strengthening the broken geological environment around the pile. The specific operation method is to determine the position depth of the broken geological layer\zone and the sand layer, and uniformly set grouting parallel to the pile foundation within the range of 1-1.5 meters around the pile foundation. The vertical position of the grouting hole needs to pass through the broken zone of the lower rock layer for 50cm, and then select P.O32.5 ordinary Portland cement to make cement slurry with a water-cement ratio of 0.5 for grouting.
[0026] Such as figure 1 As shown, for a pile foundation with a diameter of 3.0m, a circle of 4.6m is arranged at the plane position with the center of the pile foundation as the center, and 6 grouting holes are arranged in each circle; figure 2 As shown, the pile foundation with a diameter of 1.8m, the plane position is centered on the center of the pile foundation, and 4 grouting holes are arranged in a circle o...