Supporting system at position of post-pouring belt of underground garage roof and construction method

A technology for underground garages and support systems, applied to pillars, artificial islands, water conservancy projects, etc., can solve the problems of inability to disassemble the post-cast belt frame body, difficult cleaning of post-cast belt sundries, occupying steel pipes, fasteners, etc., and achieve saving Manpower, simple construction, and the effect of improving the turnover rate

Inactive Publication Date: 2017-01-11
ZHONGTIAN CONSTR GROUP
View PDF5 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] Since the concrete at the post-cast belt of the roof is generally required to be poured 60 days after the completion of the main structure, part of the frame of the post-cast belt cannot be disassembled when the main formwork is removed
[0004] This formwork support system has steel pipes and fasteners that occupy turnover, and it is difficult to clean up debris such as garbage gathered at the post-casting belt during the main construction process.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Supporting system at position of post-pouring belt of underground garage roof and construction method
  • Supporting system at position of post-pouring belt of underground garage roof and construction method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0024] The present invention will be further described in detail below in conjunction with the accompanying drawings and through specific embodiments.

[0025] A support system at the post-cast belt of the roof of an underground garage, such as figure 1 , figure 2 As shown, it includes a garage floor 3, a garage roof 1, and a structural column 2. The garage roof is reserved with a post-casting belt 4, and two rows of structures are symmetrically installed between the garage floor and the garage roof on the left and right sides of the post-casting belt. Columns, the distance between each row of structural columns is 4m, and the structural columns are poured together with the garage floor and garage roof.

[0026] In this embodiment, the structural column is a reinforced concrete structure, and the size of the structural column is 200mm*300mm. The steel bars of the structural column are four third-grade No. 14 steel bars, and the stirrups are first-grade 6.5 round steel with a...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a supporting system at the position of a post-pouring belt of an underground garage roof and a construction method. The supporting system comprises a garage bottom plate, the garage roof and constructional columns. The post-pouring belt is reserved on the garage roof. The two rows of constructional columns are symmetrically installed on the portions, on the left side and the right side of the post-pouring belt, between the garage bottom plate and the garage roof. Pouring is conducted on the constructional columns, the garage bottom plate and the garage roof together for forming. According to the supporting system, the constructional columns are used as supporting formworks of a post-pouring belt formwork, pouring is conducted on the constructional columns, the garage bottom plate and the garage roof together, construction is easy, the turnover rate of the supporting system is increased, and by arranging the constructional columns, stability of a garage is effectively improved. The post-pouring belt subjected to pouring through the supporting system is high in quality and free of impurities, does not need subsequent processing and saves manpower. The construction method is simple, scientific and reasonable in design and easy to achieve, manpower is effectively saved, the turnover rate of the formworks is increased, the stability of the whole garage is effectively improved by additionally arranging the constructional columns, and the wide application and popularization value is achieved.

Description

technical field [0001] The invention belongs to the field of construction, in particular to a support system and a construction method at the post-cast belt of the roof of an underground garage. Background technique [0002] During the construction of the roof of the underground garage, when the formwork is supported at the post-cast belt of the underground garage roof, steel pipes and fasteners are usually used to set up an independent formwork support system for the post-cast belt, which is erected together with the main frame. [0003] Since the concrete at the post-casting zone of the roof is generally required to be poured 60 days after the completion of the main structure, part of the frame of the post-casting zone cannot be disassembled when the main formwork is removed. [0004] This formwork support system has steel pipes and fasteners that take up turnover, and it is difficult to clean up debris such as garbage gathered at the post-casting belt during the construct...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E02D29/045E04B1/20E04C3/34
CPCE02D29/045E02D2300/002E04B1/0007E04B1/20E04C3/34
Inventor 朱健洪宋巍许峰曲怀国陈永伟刘光辉
Owner ZHONGTIAN CONSTR GROUP