Ground prefabricated foundation of communication tower and mounting method of ground prefabricated foundation

An installation method and ground-based technology, applied in infrastructure engineering, construction, etc., can solve the problem of long cycle, and achieve the effect of improving the success rate, shortening the cycle, and widening the scope of use.

Inactive Publication Date: 2017-02-22
江苏铭远杆塔有限公司
View PDF4 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] In order to solve the problems of the prior art, the present invention provides a ground-based prefabricated foundation for communication towers, which solves the problem of long periods for the original reinforced concrete on-site pouring, and greatly shortens the period, saves the transportation workload and saves labor and cost

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Ground prefabricated foundation of communication tower and mounting method of ground prefabricated foundation

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0016] The invention provides a ground type prefabricated foundation of a communication tower, the structure of which is as follows figure 1 As shown, it includes a plurality of equidistant parallel distributed strip foundations 1 and several equidistant parallel distributed foundation steel frame beams 2, the described foundation steel frame beams 2 are perpendicular to the strip foundation 1, and each foundation steel frame beam 2 is All the strip foundations 1 are fixed by preset bolts on the strip foundations 1 .

[0017] As a further improvement, lifting lugs are fixed at both ends of the strip foundation 1 .

[0018] The present invention also provides a method for installing a ground-based prefabricated foundation of a communication tower, comprising the following steps:

[0019] 1) Excavate the foundation pit, dig the foundation pit well and use stones to tamp the bottom of the foundation pit;

[0020] 2) The crane lifts the strip foundation and places it on the bott...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention provides a ground prefabricated foundation of a communication tower and a mounting method of the ground prefabricated foundation. The ground prefabricated foundation of the communication tower comprises a plurality of strip-shaped foundation bodies which are distributed at equal intervals in parallel and a plurality of foundation steel frame beams which are distributed at equal intervals in parallel. The foundation steel frame beams are perpendicular to the strip-shaped foundation bodies. Each foundation steel frame beam is fixed to all the strip-shaped foundation bodies through prearranged bolts on the strip-shaped foundation bodies. By adoption of the ground prefabricated foundation of the communication tower and the mounting method of the ground prefabricated foundation, the problem that in the prior art, the cycle of field pouring of reinforced concrete is long is solved, the cycle is greatly shortened; and meanwhile, the transportation workload is reduced, and labor and cost are saved.

Description

technical field [0001] The invention relates to the field of communication equipment, in particular to a ground-type prefabricated foundation of a communication tower and an installation method thereof. Background technique [0002] In the existing communication tower manufacturing technology, cast-in-place reinforced concrete foundations are generally used. The foundation construction method has a long construction period, discharges mud and sewage on site, destroys greening and damages roads. [0003] The traditional method of foundation construction requires excavation, watering, and natural maintenance for 20-28 days, and the reinforced concrete foundation is prone to generate construction waste, which has a great impact on the environment of the construction site. Contents of the invention [0004] In order to solve the problems of the prior art, the present invention provides a ground-based prefabricated foundation for communication towers, which solves the problem ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): E02D27/42
CPCE02D27/42
Inventor 鲁荣奇
Owner 江苏铭远杆塔有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products