A technology of reinforced concrete and production process, which is applied in the direction of manufacturing tools, strengthening molding, ceramic molding machines, etc., to save the construction time, shorten the time used, and standardize the construction work.
Inactive Publication Date: 2017-04-26
CHINA RAILWEY ENG SERVICE CO LTD
View PDF5 Cites 29 Cited by
Summary
Abstract
Description
Claims
Application Information
AI Technical Summary
This helps you quickly interpret patents by identifying the three key elements:
Problems solved by technology
Method used
Benefits of technology
Problems solved by technology
The construction technology of shield method includes earth pressure balance type, mud-water balance type and mixed type shield, and the cross-sectional forms include circular, elliptical, rectangular, compound circular, horseshoe, etc., and the types of segments are also developed accordingly. At present, double circular The construction technology of shield tunneling and the production level of double-circle high-precision precast concrete segments have reached the international leading level, but the production level of concrete segments for horseshoe-shaped tunnels has not yet matured in China
Method used
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more
Image
Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
Click on the blue label to locate the original text in one second.
Reading with bidirectional positioning of images and text.
Smart Image
Examples
Experimental program
Comparison scheme
Effect test
Embodiment Construction
[0025] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.
[0026] Such as figure 1 Shown, a kind of production technology of prefabricated reinforced concrete segment, its step comprises:
[0027] a. Mold cleaning and oiling. When cleaning the mold, clean the concrete residue on the inner periphery and bottom of the mold. Use steel balls to polish the mortar on the corners of the inner cavity of the mold. leak coating;
[0028] b. Assembling the mold, close the mold in the order of the first end template and the rea...
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
PUM
Login to view more
Abstract
The invention discloses a production process for prefabricated reinforced concrete duct pieces. The production process comprises the following steps of: a, clearing a mould and removing oil of the mould; b, assembling the mould; c, detecting precision of the mould; d, mounting a steel reinforcement framework and embedded parts; e, pouring and vibrating concrete, wherein vibrating time is controlled to be 4-10 minutes; f, molding and plastering concrete; g, carrying out steam curing on the duct pieces, resting for 3-4 hours and starting heating and steam-curing after vibrating is ended, wherein the duct piece steam-curing comprises four stages of a still resting stage T, a heating stage S, a constant-temperature stage H and a cooling stage J; h, de-molding the duct pieces; i, numbering and marking the duct pieces, and checking appearance to repair; j, carrying out water curing on the duct pieces; and k, storing the duct pieces. According to the production process disclosed by the invention, factory construction time can be saved, the whole construction period is effectively shortened, and factory construction cost is reduced; a fixed mould is on a designated position, and therefore, designated duct pieces with errors are favorably managed, and problem causes can be quickly determined; tunnel shield reinforced concrete duct pieces with high quality can be produced; and construction operation is normalized, programmed and standardized.
Description
technical field [0001] The invention relates to the field of shield segments, in particular to the production of prefabricated reinforced concrete segments in horseshoe-shaped shield construction. Background technique [0002] Shield method construction is a world-advanced underground tunnel construction technology. Using shield method for tunnel excavation has the advantages of fast construction speed, high lining quality, and small environmental impact. The prefabricated silicon segment used as a supporting structure requires With high strength, high precision, high quality, high impermeability and high appearance quality, it plays a vital role in the long-term stability and safe operation of the tunnel. The production of prefabricated segments of shield tunnels, its technology is developed with the development of tunnel construction technology, especially the development of shield tunnel construction technology. The construction technology of shield method includes earth...
Claims
the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more
Application Information
Patent Timeline
Application Date:The date an application was filed.
Publication Date:The date a patent or application was officially published.
First Publication Date:The earliest publication date of a patent with the same application number.
Issue Date:Publication date of the patent grant document.
PCT Entry Date:The Entry date of PCT National Phase.
Estimated Expiry Date:The statutory expiry date of a patent right according to the Patent Law, and it is the longest term of protection that the patent right can achieve without the termination of the patent right due to other reasons(Term extension factor has been taken into account ).
Invalid Date:Actual expiry date is based on effective date or publication date of legal transaction data of invalid patent.