An underground comprehensive pipe corridor structure
A comprehensive pipe gallery and joint technology, which is applied to underwater structures, infrastructure engineering, buildings, etc., can solve the problems of low joint strength, water accumulation in pipe gallery, water seepage, etc., to achieve convenient construction, increase connection strength, Reduce the effect of crack generation
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0018] Such as figure 1 As shown, an underground comprehensive pipe gallery structure in this specific embodiment includes a top plate 1, a bottom plate 2, and 4 side walls arranged at intervals along the transverse direction, and the 4 side walls separate the space between the top plate 1 and the bottom plate 2 There are 3 pipe galleries, and the side wall is provided with side wall mesh reinforcement 4, and the upper and lower ends of the side wall mesh reinforcement 4 can protrude from the side wall respectively and extend into the top plate 1 and the bottom plate 2 respectively. A vertical reinforcement anchoring end 5 is formed inside so that the side wall is fixedly connected with the top plate 1 and the bottom plate 2 .
[0019] In this specific embodiment, each side wall includes two prefabricated wall panels 3 spaced apart and arranged in parallel. Concrete interlayer is poured, the upper and lower ends of the outermost prefabricated wall panels 3 of the two outermos...
Embodiment 2
[0027] Such as figure 2 As shown, as another specific embodiment of the present invention, the vertical tendon anchoring end 5 is a pier head structure, and the horizontal tendon anchoring end 7 is a pier head structure.
[0028] In a specific implementation process, each side wall is composed of multiple sections in the longitudinal direction, and two adjacent sections of the side wall are connected by a fixing piece, and both sides of the fixing piece respectively extend into the concrete interlayer of the connected side wall.
[0029] The fixing member includes an overlapping reinforcement cage extending vertically, the section of the overlapping reinforcement cage is rectangular and the center line is located on the plane of the joint between two adjacent sections of side walls.