Construction method applied to split installation of offshore wind power generators
A technology for wind turbines and construction methods, which is applied in the directions of installing/supporting wind turbine configuration, wind energy power generation, sustainable manufacturing/processing, etc. Small impact and the effect of improving installation work efficiency
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0022] Such as figure 1 and figure 2 As shown, this embodiment provides a construction method for separate installation of offshore wind turbines. The wind turbines are located on the platform of the wind turbine foundation 10, wherein the wind turbines include towers and are located above the towers. The fan includes the following steps: step S1: sinking the pile foundation of the fan foundation 10; step S2: manufacturing the auxiliary platform 20, and installing the auxiliary platform 20 next to the fan foundation 10, so that the The auxiliary platform 20 is close to the fan foundation 10; step S3: install a spreader on the auxiliary platform 20, and continue to inspect the cable pipes, ship berthing facilities, and anti-collision structures of the fan foundation 10 under the cooperation of the spreader. Install and carry out the construction of cap steel bars, templates and concrete structures; step S4: use the sling on the auxiliary platform 20 to hoist the tower to the ...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com