Dynamic Calculation Method of Submarine Cable Operation Cost
A calculation method and operation cost technology, applied in the direction of calculation, computer-aided design, instruments, etc., can solve the problems of complex construction process of submarine cable laying, high precision requirements, and excessive waste of construction costs that cannot be quantitatively assessed, and achieve the realization of construction and construction. The effect of cost optimization
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0029] In order to express the present invention more clearly, the present invention will be further described below in conjunction with the accompanying drawings.
[0030] A method for dynamically calculating cost of a submarine cable operation realized by the present invention, the method realizes the cost calculation of controlling the construction period of each link in the submarine cable construction process through a service terminal, and is characterized in that the method includes the following steps:
[0031] S01. Set the initial routing submarine cable type according to the desktop research results, and provide the default routing submarine cable type when creating the route, which is used to draw the routing style.
[0032] S02 Establish a seabed profile model according to the surveyed seabed parameters, use CAD files to pick up water depth layer data and geological layer data, and establish a seabed profile diagram;
[0033] S03 Set the submarine cable types corre...