Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method for fast breaking pile head of cast-in-place pile

A construction method and cast-in-place pile technology, applied in sheet pile walls, infrastructure engineering, construction, etc., can solve the problems of bending and damage of steel bars, low work efficiency, affecting construction quality and progress, etc., to achieve convenient construction and installation, and improve construction efficiency. Effect

Inactive Publication Date: 2018-01-19
YUNNAN NO 5 CONSTR ENG
View PDF3 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

This will cause bending damage to the steel bar when the pile head is removed, and it is easy to cause the steel bar to break from the bottom and need to be re-welded
This construction method has low work efficiency, it is difficult to ensure the construction quality of the steel bars after the pile head is broken, and it requires a lot of labor, which seriously affects the construction quality and progress

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method for fast breaking pile head of cast-in-place pile
  • Construction method for fast breaking pile head of cast-in-place pile
  • Construction method for fast breaking pile head of cast-in-place pile

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0021] A construction method for quickly removing the head of a cast-in-situ pile, comprising the following steps:

[0022] (1) if figure 1 As shown, when the reinforcement cage is processed and manufactured, the main reinforcement 1 above the pile top elevation is not bent, and the parallel state is kept; each main reinforcement is placed at the pile top elevation ( figure 1 The upper part of the middle horizontal line A) is inserted into the casing 2, and the casing is made of soft plastic pipe, and the upper and lower ends of the casing are wound and tightened with iron wires. The function is to prevent the pile head reinforcement from sticking to the poured concrete knot; the inner diameter of the casing is 3-5mm thicker than the steel bar;

[0023] (2) Carry out pile foundation concrete pouring until it exceeds the design elevation of the pile top; figure 1 , figure 2 As shown, when pouring to the pile top elevation, the reinforcement ring 3 that meets the overall hoi...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

A construction method for fast breaking a pile head of a cast-in-place pile includes the steps that the top end of each main steel bar of a steel bar cage is sleeved with a casing pipe, and an upper end port and a lower end port of each casing pipe are sealed; then pile foundation concrete grouting is performed till the designed elevation of the pile top is achieved; when grouting is performed atthe position of the elevation of the pile top, steel bar hoisting rings are pre-buried in pile head concrete above the elevation of the pile top; after the pile body concrete is solidified, earthworkaround the pile head is excavated; the portion needing pile cutting is measured and identified; after drilled holes are evenly distributed along the circumference of the identified position, the pilehead concrete is separated through a splitter; and the pile head concrete is hoisted out and carried away. The construction method effectively solves damage to the steel bars and a pile body in the construction process, improves the construction efficiency and guarantees the engineering quality.

Description

technical field [0001] The invention relates to the technical field of construction methods of cast-in-situ piles in house construction, in particular to a construction method for rapidly removing the heads of cast-in-situ piles. Background technique [0002] When pouring cast-in-situ piles, the concrete aggregates sink during the vibration process, and the cement slurry carries air bubbles back upwards, resulting in low concrete strength at the top of the pile. In order to ensure the concrete strength of the pile foundation, after the pouring of the pile foundation is completed, the part of the pile head higher than the design elevation of the pile top is removed to expose the steel bars, and then the steel bars are used to connect the steel bars of the upper cap structure to carry out the pouring of the superstructure. At present, the commonly used method of removing the pile head is: chiseling manually with small machines, or using a grinder to cut the pile head at the de...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D9/00
Inventor 李涛童秀东方云波郑开盛王文洪张栋梁陈卓睿李卫王云志
Owner YUNNAN NO 5 CONSTR ENG
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products