Installation method of building doors and windows
An installation method, a technology for building doors and windows, applied in the direction of fastening/covering of joints, detecting the appearance of fluid at the leak point, using liquid/vacuum for liquid tightness measurement, etc., can solve the problem of high operational risk and existing problems. Potential safety hazards and other issues, to achieve the effect of convenient construction, perfect water tightness, and perfect testing process
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0044] The installation method includes the following steps:
[0045] Step 1: Before installation, check the door and window openings one by one, and control the painting size of the opening and the gap between the door and window frame 2 to 15mm;
[0046] Step 2: Mark the positioning processing point, install the fixing part 1 on the positioning processing point with screws, set the fixing part 1 as a few characters, check the distance and position of the several characters, and set the distance of the several characters on each side wall of the window opening to 400mm, the number of codes on each side wall is set to 2;
[0047] Step 3: Move the door and window frame 2 to the opening, check the position of the door and window frame 2, and use an electric screwdriver to pass the self-tapping screw through the door and window frame 2 and fix it with the fixing piece 1;
[0048] Step 4: Filling the door and window frame 2: fill the periphery of the door and window opening with ...
Embodiment 2
[0057] The difference between embodiment 2 and embodiment 1 lies in the way of stuffing in step 4.
[0058] The installation method includes the following steps:
[0059] Step 1: Before installation, check the door and window openings one by one, and control the painting size of the opening and the gap between the door and window frame 2 to 15mm;
[0060] Step 2: Mark the positioning processing point, install the codes on the positioning processing point with screws, and check the distance and position of the codes. The distance between the codes on each side wall of the window opening is set to 400mm. The number of several character codes is set to 2;
[0061] Step 3: Move the door and window frame 2 to the opening, check the position of the door and window frame 2, and use an electric screwdriver to pass the self-tapping screw through the door and window frame 2 and fix it with the fixing piece 1;
[0062] Step 4: Filling of the door and window frame 2: Fill the periphery ...
Embodiment 3
[0071] The difference between embodiment 2 and embodiment 1 lies in the different parameters of step 1, step 2 and step 5, the difference of filling method in step 4 and the difference of the proportion of mortar material.
[0072] The installation method includes the following steps:
[0073] Step 1: Before installation, check the openings of the doors and windows one by one, and uniformly control the painting size of the openings and the gap between the door and window frames 2 to 18mm;
[0074] Step 2: Mark the positioning processing point, install the codes on the positioning processing point with screws, review the distance and position of the codes, set the distance between the codes on each side wall of the window opening to 450mm, and set the codes on each side wall to 450mm. The number of several character codes is set to 2;
[0075] Step 3: Move the door and window frame 2 to the opening, check the position of the door and window frame 2, and use an electric screwdr...