Integrated excavation construction method for transition from shaft construction passage to large cross-section tunnel

A technology of construction access and construction method, applied in tunnels, tunnel linings, shaft equipment, etc., can solve the problems of long excavation period, construction safety, biased pressure, etc., and achieve the effect of simplifying the process, shortening the construction period, and easy to construct.

Pending Publication Date: 2018-11-20
BEIJING MUNICIPAL ROAD & BRIDGE
View PDF0 Cites 14 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] The purpose of the present invention is to overcome the problem of uneven force and bias pressure on the surrounding rock and support in the conversion section of the subway station tunnel in the construction channel conversion, and to overcome the existing construction scheme by using the construction channel to transfer to the subway station tunnel to complete the overall opening of the station. Disadvantages of long mining cycle
[0008] 2) Use the double-side-wall pilot pit method to excavate large-section tunnels to open up internal cross passages, improve the traditional middle partition support, and erect frame beams instead to ensure the safe construction of internal cross passages, which is convenient for slag and slag discharge between the left and right pilot tunnels. The construction of support and Fengshui circuit further solves the safety problem of opening a cross passage inside the double side wall pilot pit method and the slow construction period of excavating the subway station

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Integrated excavation construction method for transition from shaft construction passage to large cross-section tunnel
  • Integrated excavation construction method for transition from shaft construction passage to large cross-section tunnel
  • Integrated excavation construction method for transition from shaft construction passage to large cross-section tunnel

Examples

Experimental program
Comparison scheme
Effect test

Embodiment example

[0071] The invention is used in the Guanshui Road Subway Station of the first-phase project of Guiyang Urban Rail Transit Line 2, and has achieved good results from the site construction conditions.

[0072] Guiyang Urban Rail Transit Line 2 is an important subway line under construction in Guiyang City, Guizhou Province. The line starts from Qijilukou Station, passes through Longdongbao International Airport, Nanming District Administrative Center and other key construction areas in Guiyang City, and ends at Passenger Transport East Station. The first phase of Line 2 (Qijilukou Station to Youzha Street Station) is the entire length of the line 27.4km, all underground. There are 24 stations in total. The average station spacing is 1162m, the maximum station spacing is 2070m, and the minimum station spacing is 645m, with a total of 5 transfer stations.

[0073] Guanshui Road Station is the 23rd station of the first-phase project of Line 2. The proposed station is an intermedi...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an integrated excavation construction method for transition from a shaft construction passage to a large cross-section tunnel. The method is characterized in that mileages of ashaft, a cross passage and an internal cross passage of a double-sidewall cross passage need to be larger than 3 times of a cross passage hole width, so that mutual interference between shaft and cross passage construction and internal cross passage construction can be avoided; transition construction for the cross passage and a subway station tunnel is carried out at a same elevation, so that abias pressure on a joint section caused by variable cross-section construction for the large cross-section tunnel and a small cross-section tunnel can be avoided; and the internal cross passage is established and a frame girder is erected during excavation of the large cross-section tunnel through the double-sidewall drift method, so that the transition construction is achieved. The method provided by the invention has the advantages that the benching tunneling method for the construction passage and the 9-step double-sidewall drift method for the subway station tunnel are integrated, so thata transition section process of the two construction methods is simplified, and the construction is facilitated.

Description

technical field [0001] The invention belongs to the technical field of large-section tunnel construction, and relates to an integrated excavation construction method for converting a vertical shaft construction channel into a large-section tunnel, in particular to a method of rock pillars in a double hole—a method of excavating in a double-side pilot pit The integrated excavation construction method of the shaft-construction channel conversion large-section tunnel improved on the basis of this paper. Background technique [0002] With the rapid development of society and the acceleration of urbanization, the scale of cities is constantly expanding, and the population of large cities and megacities is dense, and the traffic for people to travel has become extremely congested. In order to meet people's travel requirements and realize the purpose of convenient and fast transportation, people gradually turn their attention to the construction of urban rail transit. Among them, ...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E21D9/14E21D11/18E21D11/10E21D20/00
CPCE21D9/14E21D11/10E21D11/18E21D20/00
Inventor 赵迎宋战平胡敏曹智淋王西波刘宪永张海生肖双全石清宇张曼华李静周鹏远霍奇
Owner BEIJING MUNICIPAL ROAD & BRIDGE
Features
  • Generate Ideas
  • Intellectual Property
  • Life Sciences
  • Materials
  • Tech Scout
Why Patsnap Eureka
  • Unparalleled Data Quality
  • Higher Quality Content
  • 60% Fewer Hallucinations
Social media
Patsnap Eureka Blog
Learn More