Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Rotary excavating and drilling half-hole mud wet-method hole formation process of collapsible loess super-length large-diameter pile foundation

A technology of collapsible loess and rotary drilling, which is applied in the direction of foundation structure engineering, sheet pile walls, buildings, etc. It can solve the problems of fast mud sedimentation, long concrete pouring time, and increased construction difficulty, so as to achieve easy quality assurance, Good effect and reduced processing cost

Inactive Publication Date: 2018-12-25
CHINA RAILWAY 23RD CONSTR BUREAU LTD +1
View PDF2 Cites 3 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

The characteristics of the long pile foundation are that the pile foundation is long, the hole diameter is large, the soil layer of the pile wall is thick, the self-stability is poor, the hole forming, the reinforcement cage installation, the concrete pouring time is long, it is easy to collapse, the mud sedimentation speed is fast, and the sedimentation volume is large, so the construction is difficult. How to quickly, safely, economically and environmentally friendly complete the construction of long pile foundations in collapsible loess areas has always been a problem that plagues construction

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0038] The TYKZ3 standard length of the Gansu Tianshuibao-Qingcheng-Yonghe section of the Yinchuan-Baise National Expressway undertaken by China Railway 23rd Bureau Group is 19.615km. There are 28 bridges on the whole line. Among them, the Wuritiangou Bridge is due to the pile length (maximum pile length 96m) , Pier height (maximum pier height 163m), large span (maximum span continuous rigid frame 180m) ranks second in the same type of bridge in Asia, the construction period is tight and difficult. There are 950 pile foundations on the whole line, all located on collapsible loess, designed as friction piles, and some piers are end-bearing piles. In view of the geological conditions of the pile foundation, more than 20 super-long and large-diameter pile foundations were constructed by rotary drilling half-hole mud wet method. The maximum construction pile length is 96m, the maximum construction pile diameter is 2.5m, and the success rate is 100%. The safety and quality are equal....

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a rotary excavating and drilling half-hole mud wet-method hole formation process of a collapsible loess super-length large-diameter pile foundation and belongs to the technicalfield of pile foundation rotary excavating and drilling hole formation. The process comprises the following steps: confirming pile foundation rotary excavating and drilling half-hole mud wet-method hole formation conditions, flattening a field, burying protection barrels, making mud, drilling holes, cleaning the holes, manufacturing reinforcement cages, mounting the reinforcement cages, mounting guide tubes, and grouting concrete. According to the half-hole mud wet-method hole formation process provided by the invention, dry-method mud-free hole formation is implemented in an upper crack sinkhole development section, a rapid speed can be achieved, a hole wall can be extruded by a drilling hopper, and the hole wall stability can be improved; mud wall protection wet-method hole formation isimplemented in a lower part, hole collapse can be effectively prevented, and a hole formation speed can be ensured; a good mud wall protection effect can be achieved, remarkable effects in reducing hole collapse and the like can be achieved, and the security can be easily ensured; holes can be cleaned through bottom blowing and slag turnover and positive circulation of high pressure water, or bydoping mud or clean of a low density at the hole bottoms to directly dilute the mud, slag settled at the hole bottoms can be completely cleaned off, the possibility that the settled slag is mixed withthe mud in pile foundation concrete can be reduced, and the quality can be easily ensured.

Description

Technical field [0001] The invention belongs to the technical field of pile foundation rotary excavation and drilling, and specifically relates to a semi-hole mud wet hole forming process for collapsible loess ultra-long and large-diameter pile foundation rotary excavation and drilling. Background technique [0002] Since the beginning of the new century, as the people’s requirements for driving comfort have increased, the design longitudinal slopes of high-grade railways and highways have gradually decreased, and there have been more and more large-span and high-pier bridges. The bearing capacity of the foundation is required to be large. In particular, most of the geology in Shaanxi and Gansu in northern my country is collapsible loess. Due to the thicker soil layer of collapsible loess and low pile side friction resistance, various long pile foundations over 50m have emerged. The characteristics of a long pile foundation are the long pile foundation, large diameter, thick soi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D27/12E02D5/38E02D15/04
CPCE02D5/38E02D15/04E02D27/12
Inventor 张旭黎龙强林恩川田宝华张大鹏周琪吴新栋刘咏梅尹智勇刘延龙
Owner CHINA RAILWAY 23RD CONSTR BUREAU LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products