Simultaneous Construction Method of Shield Crossing Piston Air Duct and Upper Structure of Piston Air Duct

A technology of synchronous construction and piston air, which is applied in the direction of infrastructure engineering, tunnels, earthwork drilling and mining, etc., can solve problems such as inability to synchronize construction up and down, inability to carry out ends, and tight construction schedules, so as to reduce the amount of earthwork backfill and increase construction efficiency , to avoid the effect of idle work

Active Publication Date: 2020-02-07
CHINA RAILWAY 12TH BUREAU GRP +1
View PDF9 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] In order to overcome the deficiencies in the prior art, the present invention provides a method for synchronous construction of the shield tunnel through the piston air duct and the upper structure of the piston air duct, which solves the problem of the shield tunnel passing through the piston air shaft in the prior art due to the underground space being affected. It is impossible to carry out end reinforcement, the construction period is tight and the construction cannot be carried out synchronously.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Simultaneous Construction Method of Shield Crossing Piston Air Duct and Upper Structure of Piston Air Duct
  • Simultaneous Construction Method of Shield Crossing Piston Air Duct and Upper Structure of Piston Air Duct
  • Simultaneous Construction Method of Shield Crossing Piston Air Duct and Upper Structure of Piston Air Duct

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0034] The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

[0035] The present invention constructs the negative second-story side wall 16 of the left line of the piston air duct and the negative second-story side wall 17 of the right line of the piston air duct by segmental flowing water, and sequentially erects the left line side wall opposite support 1 and the right line side wall opposite support 2 Realize the force conversion of the support system in the enclosure structure; the concrete guide platform 4 on the lef...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to the technical field of subway construction and particularly relates to a method for synchronously constructing a shield crossing piston air duct and a piston air dust upper structure. The segmented flow construction is employed by a second floor underground, the conversion of an inner support force system is reasonably completed, and a reliable reaction support system is provided for the passing of a shield. During the construction of a soil mold, a pit precipitation well is introduced out, and the stability of a piston air duct bottom plate structure in construction is ensured. After the construction of a middle plate, a middle plate hole is blocked by using a hole blocking plate, therefore, piston structure upper and lower structures are completely isolated, a closed space is provided for the shield crossing piston air duct, an effective reaction support is formed, an end reinforcement process is avoided, and the construction of the piston air dust upper structure is carried out simultaneously. According to the method, the problem that the shield crossing piston air duct and the piston air dust upper structure cannot be synchronously constructed is effectively solved, and the method has the advantages of reasonable operation, high safety and reliability, the effective avoidance of slow work, and the effective shortening of a construction period.

Description

technical field [0001] The invention relates to the technical field of urban rail transit and subway construction, and more specifically, relates to a method for synchronous construction of a shield passing through a piston air duct and an upper structure of the piston air duct. Background technique [0002] With the rapid development of my country's urban rail transit construction, the intensity of subway construction continues to increase. Urban subway construction is affected by many factors such as pipeline relocation, traffic diversion, land acquisition and demolition, etc., resulting in a tight subway construction schedule. The main structure of the piston air shaft is generally buried deep, and it is faced with multiple receiving and launching of shield tunneling within a short distance. The risk of construction operation is high, and the reinforcement space at the end is limited and the reinforcement period is long, which brings great risks to construction safety. R...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Patents(China)
IPC IPC(8): E21D11/38E21D11/08E21D11/10E21D11/14E21D9/06E02D19/10
CPCE02D19/10E21D9/06E21D11/08E21D11/10E21D11/14E21D11/38
Inventor 武锐余浩屈海磊支卫东任巍杰苑申贺栋栋吴金燕
Owner CHINA RAILWAY 12TH BUREAU GRP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products