A construction method for stabilizing interlayer rock in tunnels with weak surrounding rock and small clear distance
A technology of weak surrounding rock and construction method, applied in tunnels, tunnel linings, earthwork drilling and mining, etc., can solve problems affecting construction speed and construction period, endangering human safety, cracking and rheology, etc., to prevent secondary lining concrete Effects of cracking, increasing construction speed, and improving integrity
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0037] The invention provides a construction method for stabilizing intermediate rock in a tunnel with weak surrounding rock and a small clear distance, which is combined below Figure 1 to Figure 5 A structural schematic diagram of the present invention is described in detail for a specific embodiment of the present invention, but it should be understood that the protection scope of the present invention is not limited by the specific embodiment.
[0038] Such as figure 1 As shown, a kind of construction method that the present invention provides a kind of weak surrounding rock small clear distance tunnel stable interlayer rock, comprises the following steps:
[0039] S1. Multi-point sampling is carried out before construction to obtain geological samples of the construction site, so as to analyze geological data and determine the final construction plan;
[0040] S2, cave entrance and interlayer rock reinforcement;
[0041] S3. The first hole is excavated by the drill and ...