Unlock instant, AI-driven research and patent intelligence for your innovation.

Anemometer tower arrangement scheme determination method based on neural network algorithm

A technology of neural network algorithm and layout scheme, which is applied in the field of determination of anemometer tower layout scheme based on neural network algorithm, can solve problems such as easy misjudgment, high risk, low-efficiency wind farm units, etc., to achieve accurate setting and avoid mistakes Judgment, beneficial to the effect of setting

Active Publication Date: 2019-04-16
POWERCHINA CHENGDU ENG
View PDF5 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

Its main disadvantages are as follows: it is greatly affected by human factors, there is no unified standard, and the distance range that the wind measuring tower can represent should be quite different for different terrain conditions. Using the engineering experience of the designer, it is easy to cause misjudgment
[0008] (2) The phenomenon that the wind measuring tower is only representative for some positions
[0009] To sum up, there is a big risk in choosing the layout plan of the wind measuring tower by the designer based on engineering experience, which directly leads to the insufficient representativeness of the wind measuring tower, which in turn affects the accuracy of the wind energy resource assessment of the wind farm, resulting in low-efficiency units in the wind farm. the emergence of

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Anemometer tower arrangement scheme determination method based on neural network algorithm

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0022] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0023] The method for determining the layout scheme of the wind measuring tower based on the neural network algorithm includes the following steps:

[0024] A. Determine the scope of the proposed wind farm and the location of each wind turbine;

[0025] B. Select the location of the first anemometer tower; when the proposed wind farm is located in a complex terrain, the first anemometer tower is located at the highest point above sea level; when the proposed wind farm is located in a flat terrain, the first anemometer tower is located within the range of the proposed wind farm the center point;

[0026] C. Select a built wind farm near the proposed wind farm or a built wind farm similar to the proposed wind farm terrain, read and organize the data of the built wind farm; reading and sorting the data of the built wind farm includes the followin...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses an anemometer tower arrangement scheme determination method based on a neural network algorithm, relates to the technical field of wind power generation, and provides a wind measurement tower arrangement scheme determination method which is beneficial to making the positions and the number of wind measurement towers in a wind field to be established more reasonable. The method comprises the following steps that A, the range of a wind power plant to be built and the position of each wind turbine set are determined; B, selecting the position of a first anemometer tower; C, selecting a certain built wind power plant near the planned wind power plant or similar to the terrain of the planned wind power plant, and reading and arranging the data of the built wind power plant; D, fitting the built neural network of the wind power plant to obtain a trained neural network model; E, neural network prediction of the planned wind power plant; And F, designing an arrangementscheme of the anemometer tower. The algorithm and the standard for determining the anemometer tower arrangement scheme are provided, it can be avoided that the anemometer tower arrangement scheme is excessively determined and influenced by human factors, misjudgment is avoided, and the positions and the number of the anemometer towers to be built in the wind field can be accurately determined.

Description

technical field [0001] The invention relates to the technical field of wind power generation, in particular to a method for determining an anemometer tower layout scheme based on a neural network algorithm. Background technique [0002] At present, the commonly used method for wind energy resource assessment of wind farms is to set up wind measuring towers in the site area, and use wind energy resource assessment software (WT, Windsim, wasp, etc.) The distribution of wind energy resources and the calculation of power generation. The wind tower data is used as the basic data, and the wind tower setting scheme directly affects the accuracy of the wind energy resource assessment of the entire wind farm, which in turn affects the accuracy of the wind power project's power generation calculation. [0003] The setting scheme of wind measuring towers involves the number and location of wind measuring towers. For the development of wind farms, the setting of wind measuring towers s...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): G06Q10/04G06Q50/06G06N3/02
CPCG06N3/02G06Q10/04G06Q50/06
Inventor 郁永静李良县熊万能
Owner POWERCHINA CHENGDU ENG