An integrated reservoir reconstruction method for open-hole well completion and sidetracking with sidetracking
A technology for open hole completion and side drilling, which is applied in wellbore/well components, drilling equipment and methods, and production fluids, etc., can solve the problems of complex construction and low efficiency, shorten the construction period, improve construction efficiency, and improve construction efficiency. The effect of simple craftsmanship
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0032] An integrated reconstruction method for open hole completion and reservoir formation of windowed sidetracking wells. After the sidetracking wells are completed, in addition to conventional wellhead devices, fracturing trucks, sand mixer trucks, instrument trucks, fracturing manifold trucks, acid tanks and For the liquid storage tank group, the fracturing manifold truck is equipped with low-pressure and high-pressure manifolds, and the instrument truck is equipped with monitoring instruments. The rated working pressure of the wellhead device is determined according to the fracturing construction pressure. Proceed as follows:
[0033] (1) if figure 2 As shown, according to the well depth of the window sidetracking point, the main wellbore 1 is suspended with a cement plug 3 to seal off the lower part of the main wellbore 1, and the upper part of the main wellbore 1 is used as the upper part of the sidetracking wellbore;
[0034] (2) Run the sidetracking BHA at sidetrack...
Embodiment 2
[0045]An integrated reconstruction method for open hole completion and reservoir formation of windowed sidetracking wells. After the sidetracking wells are completed, in addition to conventional wellhead devices, fracturing trucks, sand mixer trucks, instrument trucks, fracturing manifold trucks, acid tanks and For the liquid storage tank group, the fracturing manifold truck is equipped with low-pressure and high-pressure manifolds, and the instrument truck is equipped with monitoring instruments. The rated working pressure of the wellhead device is determined according to the fracturing construction pressure. Proceed as follows:
[0046] (1) if figure 2 As shown, according to the well depth of the window sidetracking point, the main wellbore 1 is suspended with a cement plug 3 to seal off the lower part of the main wellbore 1, and the upper part of the main wellbore 1 is used as the upper part of the sidetracking wellbore;
[0047] (2) Run the sidetracking BHA at sidetracki...
Embodiment 3
[0058] An integrated reconstruction method for open hole completion and reservoir formation of windowed sidetracking wells. After the sidetracking wells are completed, in addition to conventional wellhead devices, fracturing trucks, sand mixer trucks, instrument trucks, fracturing manifold trucks, acid tanks and For the liquid storage tank group, the fracturing manifold truck is equipped with low-pressure and high-pressure manifolds, and the instrument truck is equipped with monitoring instruments. The rated working pressure of the wellhead device is determined according to the fracturing construction pressure. Proceed as follows:
[0059] (1) if figure 2 As shown, according to the well depth of the window sidetracking point, the main wellbore 1 is suspended with a cement plug 3 to seal off the lower part of the main wellbore 1, and the upper part of the main wellbore 1 is used as the upper part of the sidetracking wellbore;
[0060] (2) Run the sidetracking BHA at sidetrack...
PUM
Login to View More Abstract
Description
Claims
Application Information
Login to View More 