A method for establishing a bridge BIM model by adopting Dynamo software

A technology for building software and component models, applied in the field of BIM models, can solve problems such as the inability to determine the route, check the coordinate error of the pile foundation, etc.

Active Publication Date: 2019-05-17
CHINA HYDROPOWER ELEVENTH ENG BUREAU ZHENGZHOU CO LTD +1
View PDF5 Cites 26 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] The purpose of the present invention is to address the deficiencies of the prior art and provide a method for building a bridge BIM model using Dynamo software, which solves the problem that the traditional method cannot determine the long route and the middle For the problem of interrupted bridge engineering route, check the coordinate error of pile foundation

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A method for establishing a bridge BIM model by adopting Dynamo software
  • A method for establishing a bridge BIM model by adopting Dynamo software
  • A method for establishing a bridge BIM model by adopting Dynamo software

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0065] The present invention will be further described below in conjunction with the accompanying drawings of the description.

[0066] like figure 1 As shown, the main steps of the method of the present invention include: processing the pile foundation coordinate table provided by the design unit to obtain relative coordinates; using Dynamo to read the pile foundation coordinate table to establish the bridge route; according to each pile number and the central pile number coordinate table Place bridge pile foundations, caps, tie beams, pier columns, cap beams, and supports according to the relationship between them; adjust the elevation parameters of each component according to the data in the pier feature elevation list in the drawing; manually complete box girders, wet joints, bridge For surface pavement and guardrail placement, Dynamo software is used to complete the modification of its elevation parameters; quickly obtain the relative coordinates of the pile foundation in...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a method for establishing a bridge BIM model by adopting Dynamo software, which belongs to the technical field of BIM models and mainly comprises the following steps of processing a pile foundation coordinate table provided by a design unit to obtain relative coordinates; reading the pile foundation coordinate table by adopting Dynamo to establish a bridge route; placing abridge pile foundation, a bearing platform, a tie beam, a pier column, a cover beam and a support according to the relation between each pile number and the central pile number coordinate table; adjusting elevation parameters of each component according to the data in the bridge pier feature elevation list in the drawing; placing a box girder, a wet joint, bridge deck pavement and a guardrail, and adopting the Dynamo software to complete the modification of elevation parameters of the box girder, the wet joint, the bridge deck pavement and the guardrail; and rapidly obtaining and restoring the relative coordinates of the pile foundation in Revit into real coordinates, and conducting the error comparison on the real coordinates and pile foundation XY coordinates provided in a constructiondrawing. The method can effectively solve the problem that a traditional method cannot determine a bridge engineering route which is long in route and interrupted in the middle.

Description

technical field [0001] The invention belongs to the technical field of BIM models, and in particular relates to a method for establishing a bridge BIM model by using Dynamo software. Background technique [0002] BIM Building Information Modeling (Building Information Modeling) or Building Information Management (Building Information Management) or Building Information Manufacturing (Building Information Manufacturing) is based on various relevant information data of construction projects, and simulates the characteristics of buildings through digital information simulation. The real information of real information, through the three-dimensional building model, realize the functions of project supervision, property management, equipment management, digital processing, engineering management and so on. It has eight characteristics of information completeness, information relevance, information consistency, visualization, coordination, simulation, optimization and graphing. T...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): G06F17/50
Inventor 高冲
Owner CHINA HYDROPOWER ELEVENTH ENG BUREAU ZHENGZHOU CO LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products