Looking for breakthrough ideas for innovation challenges? Try Patsnap Eureka!

Construction method of reinforced concrete box girder

A construction method and technology of steel box girder, applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems affecting the opening plan, the tight construction period of Daxing Airport, etc., and achieve close contact between the top surface of the scaffold and the bottom surface of the flange plate, The effect of reducing material input and increasing safety

Inactive Publication Date: 2019-06-04
BEIJING NO 2 MUNICIPAL CONSTR ENG LTD
View PDF10 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] The one-span steel-concrete box girder connected to the swivel girder can only be constructed after the swivel girder completes its rotation. However, the construction period of Daxing Airport is tight. Formwork installation, pouring, maintenance, formwork removal and other processes are required, and it takes at least 20 days, which seriously affects the opening plan

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of reinforced concrete box girder
  • Construction method of reinforced concrete box girder
  • Construction method of reinforced concrete box girder

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0037] Embodiment 1: This embodiment is described with the construction of lead wires at Daxing Airport: refer to figure 2 , the one-span steel-concrete box girder connected to the swivel girder includes two steel-concrete box girders arranged in parallel, namely the first steel-concrete box girder 1 and the second steel-concrete box girder 2, and the space between the two steel-concrete box girders A post-casting belt 51 is provided; each piece of steel-concrete box girder includes a steel box girder body 3 , a concrete bridge deck 5 and a flange plate 4 .

[0038] A construction method for a steel-concrete box girder disclosed by the present invention comprises the following construction steps:

[0039] Step 1: If figure 1 As shown, a strip concrete base 92 is constructed on the ground near the position where the beam body is to be installed, and a plurality of vertical steel pipe supports 93 are installed on the side of the base 92, and then two steel box girder bodies 3 ...

Embodiment 2

[0052] When all the bridges are steel-concrete box girders, the steel-concrete box girders of all spans can be constructed on the ground for the bridge deck and flange plates, and then hoisted as a whole. Before hoisting, it is enough to set the scaffolding unit for support on the same side of the pier.

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention relates to a construction method of a reinforced concrete box girder, which comprises the following construction steps: 1, placing a steel box girder body on the ground, and pouring andmaintaining bridge deck concrete and flange plate concrete on the ground; 2, installing scaffold units on the ground on the same outer side faces of two bridge piers, and the scaffold units extend into the bottoms of flange plates of a first reinforced concrete box girder; 3, hoisting the first reinforced concrete box girder, loosening hooks, stressing the scaffold units, supporting the flange plates, and therefore preventing the reinforced concrete box girder from overturning due to the eccentric effect; and 4, hoisting the second reinforced concrete box girder, wherein the second reinforcedconcrete box girder is not loosened after being in place, and using a long-strip angle steel to weld with two steel box girder bodies, so that the two steel box girders are pulled and connected into awhole, and the second reinforced concrete box girder is prevented from overturning. The construction method has the technical effects that the construction period of the reinforced concrete box girder is short, and hoisting is safe.

Description

technical field [0001] The invention relates to the technical field of steel-concrete bridge construction, in particular to a construction method of a steel-concrete box girder. Background technique [0002] In the bridge construction of the approach line of Beijing Daxing Airport, steel-concrete box girders were used. Steel-concrete box girders use steel box girders as the main structure, pour concrete bridge decks on the upper surface of the steel box girders, and pour concrete flange plates on the outside of the steel box girders. Each span of the bridge is spliced ​​by two parallel steel-concrete box girders. The conventional construction process is: fabrication of steel box girders—delivery of steel box girders to the site—hoisting of the first steel box girder to the bridge pier—hoisting of the second steel box girder to the bridge pier—connection of two steel box girders— —Installing the flange slab formwork and brackets——Pouring bridge deck concrete and flange slab...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
IPC IPC(8): E01D21/00
Inventor 逯平赵昕李亚利车青森赵迪
Owner BEIJING NO 2 MUNICIPAL CONSTR ENG LTD
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products