Forward-reverse combined construction method for foundation pit of non-permanent vertical support system

A technology of vertical support and construction method, which is applied in basic structure engineering, excavation, construction, etc., can solve the problems that the verticality of steel columns cannot meet the requirements of high precision, the construction site of the basement roof cannot be used, and the environmental impact of the reverse method cannot be achieved. Achieve the effect of saving engineering cost, large support stiffness and reducing impact

Active Publication Date: 2019-06-28
SHANGHAI CONSTRUCTION GROUP +1
View PDF4 Cites 5 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0004] However, in some areas where there is a shortage of equipment and professional labor, the implementation of the conventional inversion method is limited due to lack of conditions or insurmountable reasons. The verticality of columns and piles is difficult to ensure, which affects the quality of the structure. If the straight method is used instead, although the construction is relatively convenient, it cannot achieve the effect of small environmental impact of the reverse method, and the basement roof cannot be used as a construction site
[0005] In additio...

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Forward-reverse combined construction method for foundation pit of non-permanent vertical support system
  • Forward-reverse combined construction method for foundation pit of non-permanent vertical support system
  • Forward-reverse combined construction method for foundation pit of non-permanent vertical support system

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0041] Combine below Figure 1 to Figure 15 Taking the underground three-story foundation pit as an example, the construction method of the foundation pit of the non-permanent vertical support system of the present invention is described in detail.

[0042] A foundation pit construction method combining forward and backward for a non-permanent vertical support system, comprising the following steps:

[0043] Step 1: Complete the construction of temporary steel columns 1, column piles 2, and enclosure structure 3 of the foundation pit, excavate the first layer of earthwork to a certain distance below the elevation of the basement roof, and pour concrete cushions as they are excavated;

[0044] Step 2: Build construction bents, and pour construction basement roof structure 4;

[0045] Step 3: Continue to excavate the second layer of earthwork to a certain distance below the floor level of the basement floor, and pour the concrete cushion as it is excavated;

[0046] Step 4: Se...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

PropertyMeasurementUnit
Diameteraaaaaaaaaa
Lengthaaaaaaaaaa
Login to view more

Abstract

The invention provides a forward-reverse combined construction method for a foundation pit of non-permanent vertical support system, and belongs to the technical field of foundation pit support designand construction, and provides a construction method which has the advantages of a reverse construction method and a forward construction method at the same time. According to the method, a beam plate with a permanent structure is adopted as a horizontal support, and a temporary vertical support member is adopted to bear a vertical force during foundation pit construction. And earthwork is excavated according to the floor from top to bottom, a structural beam plate is poured, a permanent vertical member is poured from bottom to top after bottom plate construction is finished, and finally temporary steel upright posts are disassembled from top to bottom to finish earthwork excavation and structural construction of the whole basement. Namely, when the permanent structural beam plate is adopted to replace a support in the foundation pit, the temporary vertical support member is adopted to bear the vertical force during the construction of the foundation pit, and the excavation of the foundation pit and the construction of the basement structure of the whole basement are achieved through reasonable construction sequence and reliable node connection.

Description

technical field [0001] The invention relates to the technical field of foundation pit support design and construction, in particular to a foundation pit construction method combining forward and reverse directions of a non-permanent vertical support system. Background technique [0002] The reverse method in the foundation pit engineering refers to the method of using the main basement beam and slab as the support in the foundation pit, excavating and constructing the basement from top to bottom according to the floor, because it has the advantages of high support rigidity, small environmental impact, saving construction period, and saving It has been applied in foundation pit engineering due to many advantages such as construction site. [0003] The vertical supporting member in the conventional upside-down method adopts "one column and one pile" that can also be used as a permanent structure, that is, supporting piles and columns are driven in the position of the structura...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
IPC IPC(8): E02D17/02E02D17/04
Inventor 张竹庭张洁龙林巧王新新
Owner SHANGHAI CONSTRUCTION GROUP
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products