A method for constructing a foundation pit
A construction method and foundation pit technology, applied in construction, excavation, foundation structure engineering, etc., to achieve the effects of good water resistance, environmental protection, and small changes
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0055] Such as figure 1 As shown, a kind of foundation pit construction method of the present embodiment comprises the following steps:
[0056] a. Determine the construction location, set positioning piles around the required construction, and install guide frames between the positioning piles;
[0057] b. The foundation pit is preliminarily formed through excavation, and protective devices are installed on the pit wall of the foundation pit;
[0058] c. Pump out the accumulated water inside the foundation pit, and install supporting devices in the foundation pit;
[0059] d. Bury the casing in the foundation pit, and drill the pile holes by means of circular drilling construction, and clean up the residual mud in the pile holes by pumping;
[0060] e. Set the support column in the pile hole, and pour concrete to fix the support column by the pump truck;
[0061] f. Use the cushion manufacturing system to manufacture the cushion, place the cushion in the foundation pit, an...
Embodiment 2
[0068] A foundation pit construction method in this embodiment is basically the same as that in Embodiment 1. Further, the fixing unit 200 of the foundation pit support device in this embodiment includes a bracket 210 for clamping the sheet pile 100, a steel bar 220 and a spine Claw 230, such as image 3 As shown, the two ends of the steel bar 220 are respectively symmetrically provided with brackets 210, and the sheet pile 100 is clamped between the brackets 210 at both ends. Set on the base 211, the inner side of the base 211 is provided with at least two annular grooves 215 matching the shape of the sheet pile 100, specifically two annular grooves 215, and in this embodiment, a wave-like extending The structure of the sheet pile 100, there is a certain overlap area between two adjacent sheet piles 100, and the fixing unit 200 is set in the overlap area to connect them, and the annular grooves 215 on both sides are just clamped on the sheet pile 100. On the inner and outer ...
Embodiment 3
[0073] A method for constructing a foundation pit in this embodiment is basically the same as the above-mentioned embodiment, furthermore, the water collection control valve 170 of the foundation pit support device in this embodiment includes an inner cylinder 172, a connecting rod 174 and a sealing ring 173, Such as Figure 7As shown, a cavity is provided in the inner cylinder 172 and a horizontal flat plate 176 is arranged in the cavity of the inner cylinder 172. The flat plate 176 divides the inner cavity of the inner cylinder 172 into an upper cavity 175 and a lower cavity 178. The plate 176 is provided with a third through hole 177 connecting the upper cavity 175 and the lower cavity 178, and the connecting rod 174 is inserted into the third through hole 177. Specifically, the plate 176 can be provided with a plurality of third through holes 177, A third through hole 177 with a larger diameter is defined in the middle of the plate 176 for the connecting rod 174 to pass th...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com