Wall scaffold installation method and pre-burying bolt wall connecting piece device
An installation method and a technology for pre-embedding bolts, which are applied to the attachments of scaffolding, construction, and housing structure support, etc., can solve the problems of difficult construction, prone to water seepage, common safety hazards, etc., to reduce construction steps, simplify construction steps, and can be operated. strong effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0038] Such as Figure 1-8 Shown, a kind of wall body scaffold installation method of the present invention, its steps are as follows,
[0039] Step 1, install the embedded components:
[0040] Construction preparation, draw the scaffolding layout, the layout of the pre-embedded component 1, the layout of the support component 2, and prepare the required scaffolding 7 related materials such as steel pipes and fasteners 8;
[0041] Lay out the positioning, determine the installation position of the pre-embedded component 1 according to the floor plan of the pre-embedded component 1, and mark it;
[0042] The formwork is installed, and after the binding of steel bars in the body of wall 4 is completed, the pouring formwork 5 of the body of wall 4 is installed,
[0043] Install the positioning plug, and open a positioning hole on the template 5, install the positioning plug 6 on the positioning hole, and the interface 111 is adapted to the positioning plug 6.
[0044] Install ...
Embodiment 2
[0055] Such as Figure 6-8 As shown, the present invention also provides a pre-embedded bolt-to-wall device, including a pre-embedded assembly 1 and a support assembly 2, the pre-embedded assembly 1 is used to be embedded in a wall 4, and the pre-embedded assembly 1 and The support components 2 are detachably connected to each other, and also include a connector 3 for connecting the embedded component 1 and the support component 2, and the embedded component 1 is provided with an interface 111 adapted to the connector 3, When embedding the pre-embedded component 1, the interface 111 on the pre-embedded component 1 is exposed outside the wall 4, and the support component 2 is connected to the interface 111 on the pre-embedded component 1 through the connector 3, realizing the pre-embedded component 1 and the support component 2 The detachable connection, and after the construction is completed, the support assembly 2 is removed, and the pre-embedded assembly 1 left in the wall ...