A kind of shock-absorbing staircase formwork for building construction and its assembly method

A technology of building construction and assembly methods, which is applied in the direction of construction, building structure, formwork/formwork/work frame, etc., can solve the problems of low construction efficiency and impassable stairs, and achieve the effect of improving construction efficiency and ensuring quality

Active Publication Date: 2021-07-13
台州宏丰建设有限公司
View PDF6 Cites 0 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0006] The above-mentioned existing technical solutions have the following defects: when the poured concrete is not solidified, the stairs cannot pass through, so it is necessary to remove the uppermost construction passage first, pour the stairs, and retain the construction passage below the stairs, so that workers can pass through the construction. Passage, go up and down floors, and maintain it before the concrete is solidified. After the concrete is solidified, remove the uppermost construction passage again, and repeat the above process until all the stairs are poured
[0007] In the above process, multiple stairs need to be poured and maintained individually, and the construction efficiency is low

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A kind of shock-absorbing staircase formwork for building construction and its assembly method
  • A kind of shock-absorbing staircase formwork for building construction and its assembly method
  • A kind of shock-absorbing staircase formwork for building construction and its assembly method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment 1

[0055] refer to figure 1 , 2 , is a shock-absorbing stair formwork for building construction disclosed by the present invention, including a main body 1, a pedal 2 and a guardrail 3, the main body 1 is erected between adjacent floors, and a pouring space 14 is provided in the main body 1, which is used for filling Concrete realizes the pouring of the stairs. The pedal 2 is arranged above the body 1 for workers to pass through and go up and down the floors, realize simultaneous pouring and maintenance of multiple stairs, and improve construction efficiency. At the same time, the guardrail 3 is arranged on one side of the body 1. It is beneficial to improve the safety of workers walking on the pedal 2.

[0056] refer to figure 2 , the body 1 includes a bottom plate 11, a side plate 12 and a cover plate 13, the bottom plate 11 is erected between adjacent floors, two side plates 12 are arranged side by side, and are located at the upper end of the bottom plate 11, refer to im...

Embodiment 2

[0078] A method for assembling a shock-absorbing stair formwork for building construction, comprising the following steps:

[0079] S1: Body 1 is fixed between adjacent floors;

[0080] S1.1: The bottom plate 11 is fixed between adjacent floors;

[0081] S1.2: The two side plates 12 are installed between the two retaining bars 111 on the bottom plate 11, and the opposite sides of the two side plates 12 abut against the retaining bars 111 respectively;

[0082] S1.3: A plurality of cover plates 13 are installed between the two side plates 12, and the two ends of the cover plates 13 are respectively embedded in the positioning grooves 121 of the two side plates 12. At the same time, the plurality of cover plates 13 And laying in turn;

[0083] S1.4: The pin 122 is inserted into the side plate 12, and the pin 122 extends between the two side plates 12, and makes the outer periphery of the pin 122 abut the cover plate 13. At the same time, the side wall of the pin 122 and the po...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention relates to a shock-absorbing stair template for building construction, which includes a body, the body includes a bottom plate, a side plate and a cover plate, side plates are arranged on both sides of the upper end of the bottom plate, and several cover plates are arranged on the bottom plate above, and located between the two side plates, the bottom plate, side plates and cover plates encircle to form a pouring space, there is also a pedal above the body, and the pedal is located above the cover plate, the bottom plate A support mechanism is provided between the pedal and the pedal. The invention has the advantages of filling concrete into the main body to complete the pouring of the stairs, and a pedal is set above the main body for workers to pass up and down floors, realize simultaneous pouring and maintenance of multiple stairs, and improve construction efficiency.

Description

technical field [0001] The invention relates to the technical field of building construction, in particular to a shock-absorbing stair formwork for building construction and an assembly method thereof. Background technique [0002] During building construction, temporary stairs are set up between adjacent floors as construction passages to meet the needs of the upper and lower floors. After the construction of the main body of the building is completed, the construction passages are removed and stairs are erected. [0003] The reason why concrete can gradually harden and increase its strength is the result of cement hydration, and the hydration of cement requires certain temperature and humidity conditions. If this condition does not exist in the surrounding environment, the concrete needs to be cured manually. For the curing of ordinary cement varieties in general environment, the curing should start 12-18 hours after the concrete is poured, and the curing time should last...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Patents(China)
IPC IPC(8): E04G13/06E04G27/00
CPCE04G13/062E04G27/00
Inventor 连永昌
Owner 台州宏丰建设有限公司
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products