[0056] A construction method for indoor stone paving of anti-aircraft drums, the specific steps are as follows:
[0057] Step 1, prefabricated stone slab: adding concrete to the prefabricated mold to prepare the prefabricated stone slab;
[0058] Step 2, cleaning the base: remove impurities, degrease, and level the indoor ground base in sequence;
[0059] Step 3, setting the leveling layer: design the leveling layer according to the ground base, and make corresponding marks, lay the leveling layer and maintain it according to the marks;
[0060] Step 4, coating the adhesive layer: apply a layer of adhesive material on the top of the leveling layer to ensure that the thickness of the adhesive material is uniform;
[0061] Step 5, laying stone slabs: Lay the prefabricated stone slabs on top of the bonding layer, and arrange them according to the preset plan;
[0062] Step 6, replenish filler: fill the gap between the laid prefabricated stone plates with filler;
[0063] Step ...
Embodiment 2
[0102] A construction method for indoor stone paving of anti-aircraft drums, the specific steps are as follows:
[0103] Step 1, prefabricated stone slab: adding concrete to the prefabricated mold to prepare the prefabricated stone slab;
[0104] Step 2, cleaning the base: remove impurities, degrease, and level the indoor ground base in sequence;
[0105] Step 3, setting the leveling layer: design the leveling layer according to the ground base, and make corresponding marks, lay the leveling layer and maintain it according to the marks;
[0106] Step 4, coating the adhesive layer: apply a layer of adhesive material on the top of the leveling layer to ensure that the thickness of the adhesive material is uniform;
[0107] Step 5, laying stone slabs: Lay the prefabricated stone slabs on top of the bonding layer, and arrange them according to the preset plan;
[0108] Step 6, replenish filler: fill the gap between the laid prefabricated stone plates with filler;
[0109] Step ...
Embodiment 3
[0148] A construction method for indoor stone paving of anti-aircraft drums, the specific steps are as follows:
[0149] Step 1, prefabricated stone slab: adding concrete to the prefabricated mold to prepare the prefabricated stone slab;
[0150] Step 2, cleaning the base: remove impurities, degrease, and level the indoor ground base in sequence;
[0151] Step 3, setting the leveling layer: design the leveling layer according to the ground base, and make corresponding marks, lay the leveling layer and maintain it according to the marks;
[0152] Step 4, coating the adhesive layer: apply a layer of adhesive material on the top of the leveling layer to ensure that the thickness of the adhesive material is uniform;
[0153] Step 5, laying stone slabs: Lay the prefabricated stone slabs on top of the bonding layer, and arrange them according to the preset plan;
[0154] Step 6, replenish filler: fill the gap between the laid prefabricated stone plates with filler;
[0155] Step ...
PUM
Property | Measurement | Unit |
---|---|---|
Particle size | aaaaa | aaaaa |
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com