Construction method of prefabricated assembly type inter-pile tie beam

A prefabricated assembly and construction method technology, which is applied in the direction of erecting/assembling bridges, bridges, bridge parts, etc., can solve the problems of increasing the bearing load of the lower pier column structure, hidden dangers of the overall structure, and increasing the cost of the project, so as to reduce the erection and construction cost. Formwork input, reduce construction cost and improve construction efficiency

Inactive Publication Date: 2020-12-29
SICHUAN JIAOTOU CONSTR ENG CO LTD
View PDF11 Cites 4 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, this construction method adds a built-in hidden flange as the connection structure on the basis of the original design. The installation is complicated and requires high precision, which increases the project cost; The plate is effectively connected, and the excess part is equivalent to the extra self-weight, which increases the bearing burden of the lower pier column structure, and makes the stress act on the joint of the flange plate, resulting in a certain safety hazard in the overall structure

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Construction method of prefabricated assembly type inter-pile tie beam
  • Construction method of prefabricated assembly type inter-pile tie beam
  • Construction method of prefabricated assembly type inter-pile tie beam

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0036] In order to make the purpose, technical solution and advantages of the present invention clearer, a construction method of a prefabricated inter-column tie beam will be described more clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention. The preferred embodiment of the construction method of the prefabricated inter-column tie beam is given in the accompanying drawings, however, the construction method of the prefabricated inter-column tie beam can be implemented in many different forms and is not limited to the implementation described herein example. On the contrary, the purpose of providing these embodiments is to make the disclosure of the construction method of the prefabricated inter-column tie beam more thorough and comprehensive.

[0037] It should be noted that like numerals and letters denote similar items in the following figures, therefore, once an item is defined in one figure, it does not req...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention discloses a construction method of a prefabricated assembly type inter-pile tie beam. The construction method comprises the steps of tie beam prefabrication, formwork support, tie beam placement, steel bar binding and formwork concrete pouring. A mode of hoisting the prefabricated tie beam is adopted to enable the prefabricated tie beam to penetrate into pile structures in a staggered mode, the prefabricated tie beam is supported through first supporting formworks which are arranged on the opposite inner sides of the adjacent pile structures at equal heights correspondingly, thenreinforcing steel bars are bound, the supporting formworks are perfected for cast-in-place construction, and connection of the tie beam and piles is completed. A cast-in-place and prefabrication combined mode is adopted for connecting the piles and the tie beam, investment of the supporting formwork is reduced, and the bridge construction quality, especially the appearance quality and the structural quality of bridge in-pile tie beam sections, is effectively improved under the condition that the design size of an original structure is not changed and the steel bar structure of the original structure is not changed, Wide application prospects are realized in the urban bridge construction, and the industrial development of buildings can be effectively promoted.

Description

technical field [0001] The invention relates to the technical field of bridge construction, in particular to a construction method of a prefabricated assembly type inter-column tie beam. Background technique [0002] The tie beam refers to the beam that acts as a tie rod, which is set between two piles or pier columns, and connects the two piles or pier columns to form a whole force, so as to improve the structure of the columns and piles, and make the pile or pier column The overall rigidity is strengthened. The tie beam set between the two pier columns is the inter-column tie beam, also known as the waist tie beam. At present, the beams between columns are all cast-in-place schemes, which mainly use artificial binding of steel bars and cast-in-place concrete on the formwork. It has high safety performance and good integrity. The quality is not easy to control and the construction period is long, which has a great impact on urban traffic. Moreover, because the tie beam i...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E01D21/00E01D19/02E02D27/12E02D5/38E02D5/66
CPCE01D19/02E01D21/00E02D5/38E02D5/385E02D5/665E02D27/12
Inventor 罗红莫志强王元赵洁盛文武能
Owner SICHUAN JIAOTOU CONSTR ENG CO LTD