A deformation monitoring and protection tooling technology, which is applied to measurement devices, earth-moving drilling, mining devices, etc., can solve the problems of difficult construction, inaccurate measurement, and easy contamination of deformation monitoring points, and achieve convenient construction, avoid pollution, No effect of measurement error
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0030] Please refer to figure 1 and figure 2 , Embodiment 1 of the present invention provides a construction method of a tunnel deformation monitoring point, and the specific construction method is as follows:
[0031] After the installation of the steel frame 1 is completed, the observation site is determined on the steel frame 1, and the monitoring point 2 is installed on the observation site. The monitoring point 2 includes a main body 20 and a reflective sticker pasted on the main body. The main body 20 is round or square except stainless steel sheet;
[0032] After observing the monitoring point 2 and recording the initial degree, wrap the reflective stickers with a blocking object;
[0033] Before spraying concrete, the protective tooling 3 is connected to the steel frame 1 around the monitoring point 2, and the monitoring point 2 is placed in the protective tooling;
[0034] After spraying the concrete and before the concrete is hardened, remove the protective tooli...
Embodiment 2
[0042] Please refer to figure 2 , Embodiment 2 of the present invention provides a protective tooling, comprising: a cover body 30 with one end open, and a bayonet 31 is provided on the open end, and the bayonet 31 is two slits 32 extending from the end face of the open end to the other end, and the two The slits 32 are arranged symmetrically and have the same cutting depth.
[0043] Further, the specific structure of this embodiment is as follows: the cover body 30 includes a cylinder and a geotextile, one end of the cylinder is open, and the other end is covered with a geotextile. In this embodiment, the geotextile is fixed on one end of the cylinder by winding steel wires. It can be taken from the geotextile hung on the surface of the primary support when the tunnel is used as the secondary lining. It has a certain anti-puncture ability, and its size can only be sealed at one end of the cylinder. It can be used locally to save costs. The cylinder is made of PVC material, th...