Construction method for integral hoisting and closure of large-section steel box girder
A construction method and overall hoisting technology, which is applied to bridges, bridge parts, bridge materials, etc., can solve the problems of long construction period and many processes, and achieve the effect of precise and fast closing
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0035] In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
[0036] In order to illustrate the technical solutions of the present invention, specific examples are used below to illustrate.
[0037] The construction method for the overall hoisting and closing of large-segment steel box girders provided by the embodiments of the present invention includes the following steps:
[0038] Step S1, construct the cantilever beam of the closing dragon span, and reserve the opening of the closing dragon as a figure-eight.
[0039] During specific construction, such as figure 1 Shown, at first adopt hanging basket 8 to carry out the concrete main body 21 construction...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com