The invention provides a mountain heavy hill asymmetric
heavy load cable crane prestressed rock anchor position calculation method, which is characterized in that traditional rock anchor position determination depends on repeated
geological survey: geological data is obtained through large-area drilling, a primary selection position is judged in combination with experience, then supplementary survey
verification is carried out, if the requirement is not met,
site selection is carried out again, and if the requirement is not met,
site selection is carried out again; the process consumes a large amount of time, the survey period of a single project usually reaches several months, the drilling difficulty in mountain areas is large, the cost is high, the construction period is easily delayed by repeated operation, and especially for asymmetric
heavy load working conditions, rock anchor
stress distribution is uneven, and a traditional experience method is difficult to accurately match geomechanical characteristics. According to the scheme, a mountain three-dimensional model is constructed to simulate
terrain and geologic features, candidate rock anchor positions are quickly screened in combination with an optimization
algorithm, and then
model parameters are verified through a small amount of
field survey, so that the drilling frequency can be greatly reduced, and the position determination period is shortened.