Irrigation and water conservancy construction method
A construction method and farmland water conservancy technology, which is applied in water conservancy projects, artificial waterways, construction, etc., can solve problems such as labor shortages, achieve the effects of reducing construction volume, speeding up construction, and reducing the amount of earthwork backfill
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0057] The construction site is flat land, and the soil at the construction site is naturally dry or slightly moist cohesive soil or silty cohesive soil. It is necessary to build a new channel 7 with a rectangular cross section. The height of the section of the concrete wall 8 of the new channel 7 is 1.3m. The thickness is 0.4m, the section of the excavation surface 1 is rectangular, the height is 1.3m, and the width is 1m. The specific steps are as follows:
[0058] Step 1. Determine the construction location, drain or intercept the water at the construction location at least one week in advance, and create conditions for the construction;
[0059] Step 2. Renovate the construction access road to meet the passage of small transport machinery. After cleaning the construction site, carry out axis stakeout, so as to facilitate construction according to the only standard during excavation;
[0060] Step 3: Carry out earthwork excavation according to the size of the section of the...
Embodiment 2
[0065] The construction site has the original channel, and the size of the original channel is larger than the new channel 7. There are many crushed stones with a particle size larger than 15cm at the bottom of the original channel. The soil at the construction site is naturally dry or slightly moist clay or silty clay. A new channel 7 with an inverted isosceles trapezoidal section is built. The concrete wall 8 of the new channel 7 has a right-angled trapezoidal section, a height of 1.3m, a thickness of the upper bottom of 0.2m, and a thickness of the lower bottom of 0.4m. The section is rectangular, with a height of 1.3m and a width of 1.4m. The specific steps are as follows:
[0066] Step 1. Determine the construction location, drain or intercept the water at the construction location at least one week in advance, and create conditions for the construction;
[0067] Step 2. Renovate the construction access road to meet the passage of small transport machinery. Clean up the c...
Embodiment 3
[0073] The construction site has the original channel, and the size of the original channel is smaller than the new channel 7. There are many gravels with a particle size greater than 15cm at the bottom of the original channel. The soil at the construction site is naturally dry or slightly moist clay or silty clay. A new channel 7 with an inverted isosceles trapezoidal section is built. The concrete wall 8 of the new channel 7 has a right-angled trapezoidal section, a height of 1.1m, a thickness of the upper bottom of 0.2m, and a thickness of the lower bottom of 0.5m. The section is rectangular, with a height of 1.1m and a width of 1.6m. The specific steps are as follows:
[0074] Step 1. Determine the construction location, drain or intercept the water at the construction location at least one week in advance, and create conditions for the construction;
[0075] Step 2. Renovate the construction access road to meet the passage of small transport machinery, clean the surface o...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com