A construction technology and municipal technology, applied in the direction of pipeline protection through thermal insulation, pipeline protection, pipeline anti-corrosion/anti-rust protection, etc., can solve problems such as pipeline damage, pipeline impact, loose soil layer, etc., to improve stability, improve buffer reduction, etc. Vibration performance, the effect of avoiding shaking
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0036] like Figure 1-Figure 5 As shown, a construction technique for protecting municipal pipelines includes the following steps:
[0037] Step 1: First, excavate the trench along the pre-made municipal pipeline laying direction mark on the pre-selected road section. The depth and width of the excavated trench need to be greater than the diameter of the municipal pipeline itself. The depth and width of the excavated trench The sizes are 80cm-100cm and 50cm-70cm respectively;
[0038] Step 2: Then excavate two empty grooves on both sides of the trench excavated in step 1, and dig a horizontal placement groove at the bottom of the trench to ensure that the width of the placement groove is greater than the width of the groove;
[0039] Step 3: Then use the drilling equipment to drill multiple fixing holes at equal intervals on both sides of the empty slot in step 2 and the placement slot;
[0040] Step 4: Then build the trenches excavated in steps 1 and 2, the side walls of th...
Embodiment 2
[0052] A construction technique for protecting municipal pipelines, comprising the following steps:
[0053] Step 1: First, excavate the trench along the pre-made municipal pipeline laying direction mark on the pre-selected road section. The depth and width of the excavated trench need to be greater than the diameter of the municipal pipeline itself. The depth and width of the excavated trench The sizes are 90cm and 60cm respectively;
[0054] Step 2: Then excavate two empty grooves on both sides of the trench excavated in step 1, and dig a horizontal placement groove at the bottom of the trench to ensure that the width of the placement groove is greater than the width of the groove;
[0055] Step 3: Then use the drilling equipment to drill multiple fixing holes at equal intervals on both sides of the empty slot in step 2 and the placement slot;
[0056] Step 4: Then lay waterproof and anti-corrosion cement on the trenches excavated in steps 1 and 2, the empty grooves and the...
Embodiment 3
[0061] A construction technique for protecting municipal pipelines, comprising the following steps:
[0062] Step 1: First, excavate the trench along the pre-made municipal pipeline laying direction mark on the pre-selected road section. The depth and width of the excavated trench need to be greater than the diameter of the municipal pipeline itself. The depth and width of the excavated trench The sizes are 90cm and 60cm respectively;
[0063] Step 2: Then excavate two empty grooves on both sides of the trench excavated in step 1, and dig a horizontal placement groove at the bottom of the trench to ensure that the width of the placement groove is greater than the width of the groove;
[0064] Step 3: Then use the drilling equipment to drill multiple fixing holes at equal intervals on both sides of the empty slot in step 2 and the placement slot;
[0065] Step 4: Then coat the trenches excavated in steps 1 and 2, the side walls of the empty slots and the placement slots, and t...