Multi-system air conditioner dispatching method and device and air conditioner
A scheduling method and multi-system technology, applied in the field of devices, air conditioners, and multi-system air conditioner scheduling methods, can solve the problems of lack of good scheduling and short service life of multi-system air conditioners, and achieve the effects of balanced service life, improved operation, and continuous start-up.
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0090] refer to figure 1 , the multi-system air-conditioning scheduling method provided in this embodiment includes the following steps:
[0091] Step S101: Obtain the cumulative running time and historical failure times of each air-conditioning system respectively.
[0092] When the multi-air conditioning system is powered on, all the air conditioning systems are not running at this time, and the cumulative running time and historical failure times of each air conditioning system are obtained at this time: when an air conditioning system is running, its running time will be accumulated , if the air-conditioning system fails, the historical failure times of the corresponding air-conditioning system are accumulated, so as to obtain the cumulative running time and historical failure times of each system. Generally speaking, the above-mentioned cumulative running time and historical failure times will be written into the storage device. When the unit needs to obtain the above d...
Embodiment 2
[0130] refer to figure 2 Compared with Embodiment 1, the multi-system air-conditioning scheduling method provided in this embodiment further includes the following steps:
[0131] Step S201: When all the air-conditioning system loads corresponding to the highest starting priority are started, after the air-conditioning system corresponding to the highest starting priority is excluded, the loss coefficients of each of the remaining air-conditioning systems are compared with each other, Re-prioritize the activation of each air conditioning system;
[0132] Step S202: When the system startup conditions are met, start the corresponding air conditioning system according to the re-determined startup priority order.
[0133] At this time, the priority of the air-conditioning system that has been running is locked and will not change, nor will it participate in the priority ranking of the unstarted air-conditioning system, ensuring that the corresponding air-conditioning system can ...
Embodiment 3
[0136] like image 3 As shown, the multi-system air conditioning scheduling method provided in this embodiment, compared with Embodiment 1, further includes the following steps:
[0137] Step S301: When the system shutdown conditions are met, the corresponding air conditioning systems are shut down according to the startup priority order.
[0138] Further, the method also includes:
[0139] Step S302: After the air-conditioning system is shut down according to the starting priority order, respectively acquire the cumulative running time and the number of historical faults of each shut-down air-conditioning system;
[0140] According to the cumulative running time and the number of historical failures, the loss coefficient of each air conditioning system is obtained;
[0141] Determine the starting priority of each air conditioning system according to the loss coefficient;
[0142] When the system start-up conditions are met, the corresponding air-conditioning systems are st...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com