Construction process of flexible shockproof joint for deposited pipe tunnel

An immersed tube tunnel and construction method technology, which is applied in the field of construction engineering, can solve the problems of inconvenient installation, high precision requirements of hydraulic crimping of joints, and inability to bear the tension of water-stop pads of pipe joints, etc.

Inactive Publication Date: 2003-02-26
SHANGHAI TUNNEL ENGINEERING CO. LTD.
View PDF0 Cites 13 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

However, since the "Ω"-shaped steel plate and "M"-shaped steel plate in the joint are formed by buckling of the steel plate, they are not completely flexible when placed in the joint; although the joint cable can overcome the shortcomings of the "Ω"-shaped or "M"-shaped steel plate , but due to the characteristics of its structural design, the hydraulic crimping accuracy of the joint is very high, so the installation is not very convenient
At the same time, neither of these two forms of longitudinal limiting members can bear the tension of the pipe joint water-stop pad during the construction of the final joint of the pipe section.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0026] Provide following construction example in conjunction with content of the present invention:

[0027] The immersed tube section in the middle of the river of an immersed tube tunnel project is 395m long and consists of four sections, one of which is 95m long and the other three sections are all 100m long. The four pipe sections are lowered on the pile foundation from the north bank of the river to the south bank of the river in turn. Among them, the E1 pipe section is lowered first and connected with the connecting well in the north of the river, then the E2 and E3 pipe sections located in the middle of the river are lowered and connected, and finally the south bank dock is lowered. E4 pipe section at the mouth. After the sinking of the pipe section is completed, the mouth of the dry dock is closed by means of cofferdam sealing, and then the water in the dock is discharged into the river. Finally, the final joint is completed under dry construction conditions, that is, ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The present invention belongs to the field of building engineering and features the longitudinal position limitation ofmuff jointed prestressed steel cable mainly. Pipe section joint rigidity is first determined based on foundation conditions; pipe section anti-seismic performance is analyzed based on the joint rigidity, and the joint form and the construction process are further determined. It has the features of simple structure for in-situ installation, flexible steel rope, no joint leakage, anticorrosive steel rope; and waterproof and anti-seismic performance, maintained even in fire.

Description

technical field [0001] The invention relates to a construction method for an immersed tube tunnel, in particular to a construction method for a flexible anti-seismic joint of an immersed tube tunnel, belonging to the field of construction engineering. Background technique [0002] The pipe joints of immersed tunnels are an important part of immersed pipe engineering. Its joints should have the following functions and requirements: first, the requirements for water tightness, that is, no leakage during the construction phase and future operation phase; second, the joints have the following functions and requirements: The ability to resist various actions, including various loads and forced deformations, such as earthquakes, temperature, and foundation deformation; the third is that the structure of the joint requires clear force, which is convenient for construction and guarantees construction quality. However, since the pipe joints that can meet the above functions and requi...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): E02D29/07E02D29/16E02D31/08
Inventor 刘千伟陈鸿沈永东
Owner SHANGHAI TUNNEL ENGINEERING CO. LTD.
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Patsnap Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Patsnap Eureka Blog
Learn More
PatSnap group products